ACWA Grants DEC - Year 4

Salmonid Habitat Restoration and Acquisition

Riparian Habitat Upland Habitat And Sediment
Project IDAK45945
Recovery Domains -
Start Date07/01/2009
End Date06/30/2010
Year2008
StatusCompleted
Last Edited05/08/2024
 
1 - 1

Description    


Two projects were funded through the ACWA program administered by the Alaska Department of Environmental Conservation. The City and Borough of Sitka continued to improve the water quality of Granite Creek by planting vegetation for additional riparian buffer protection and the Juneau Watershed Partnership constructed two stormwater treatment systems.

Project Benefit    


Salmon production is dependent on healthy habitat and sufficient water of high quality. This project will benefit salmon resources and users by protecting or improving salmon habitat and water quality in water bodies that are deemed high priority.

Accomplishments

Metric Completed Originally
Proposed
Riparian Habitat
  Stream Miles Treated .10 .10
  Acres Treated .1 .2
Upland Habitat
  Acres Treated .2 .2

Funding Details

SourceFunds
PCSRF$36,690
Other$29,446
Report Total:$66,136


Project Map



Worksites

Juneau    


  • Worksite Identifier: Juneau
  • Start Date:
  • End Date:
Area Description

No Area Description data was found for this worksite.

Location Information

  • Basin: Northern Southeast Alaska (190103)
  • Subbasin:
  • Watershed:
  • Subwatershed:
  • State: Alaska
  • Recovery Domain:
  • Latitude: 58.38357608228593
  • Longitude: -134.57907199859005

ESU

    No ESU data was found for this worksite.

Map

Photos

Metrics

Metrics
  • C.0 Salmonid Habitat Restoration and AcquisitionY (Y/N)
    •      . . C.0.a Habitat restoration and acquisition funding 21,001.00
    •      . . C.0.b Length of stream treated/protected .10
    •      . . C.0.c
      Project identified in a Plan or Watershed Assessment
      none
    •      . . C.0.d.1 Project Monitoring (LOV)
    •      . . C.0.d.2 Monitoring Location (LOV)
    •      . . C.0.d.3
      Monitoring text (from Phase I)
      The following types of monitoring will take place onsite: effectiveness and biological monitoring.
    •      . . C.6 Upland Habitat And Sediment ProjectY (Y/N)
      •      . . . . C.6.a Upland Habitat / Sediment Funding 21,001.00
      •      . . . . C.6.b.1 Acres of upland habitat area treated .1
      •      . . . . C.6.b.2 Miles of road treated in upland area
      •      . . . . C.6.c.1 Road drainage system improvements and reconstructionY (Y/N)
        •      . . . . . . C.6.c.2 Miles of road treated for drainage system improvements and reconstruction .00
      •      . . . . C.6.e.1 Erosion control structures installedY (Y/N)
        •      . . . . . . C.6.e.2 Acres treated with erosion control structures .1
        •      . . . . . . C.6.e.3 Erosion / sediment control installations 1

Sitka    


  • Worksite Identifier: Sitka
  • Start Date:
  • End Date:
Area Description

No Area Description data was found for this worksite.

Location Information

  • Basin: Central Southeast Alaska (190102)
  • Subbasin:
  • Watershed:
  • Subwatershed:
  • State: Alaska
  • Recovery Domain:
  • Latitude: 57.10521120991309
  • Longitude: -135.38006544112304

ESU

  • Un-Named ESU Chum
  • Un-Named ESU Coho
  • Un-Named ESU Pink

Map

Photos

Metrics

Metrics
  • C.0 Salmonid Habitat Restoration and AcquisitionY (Y/N)
    •      . . C.0.a Habitat restoration and acquisition funding 45,135.00
    •      . . C.0.b Length of stream treated/protected 1.50
    •      . . C.0.c
      Project identified in a Plan or Watershed Assessment
      Alaska Department of Environmental Conservation. 2002. Total Maximum Daily Load (TMDL)for Sediment and Turbidity in the Waters of Granite Creek in Sitka, Alaska
    •      . . C.0.d.1 Project Monitoring (LOV)
    •      . . C.0.d.2 Monitoring Location (LOV)
    •      . . C.0.d.3
      Monitoring text (from Phase I)
      The following types of monitoring took place onsite, upstream and downstream of the sites: implementation and effectiveness monitoring, monitoring for compliance with project design and post-treatment, biological and physical monitoring.
    •      . . C.5 Riparian Habitat ProjectY (Y/N)
      •      . . . . C.5.a Riparian Habitat Funding 22,567.00
      •      . . . . C.5.b.1 Total riparian miles streambank treated .10
      •      . . . . C.5.b.2 Total Riparian Acres Treated .1
      •      . . . . C.5.c.1 Riparian plantingY (Y/N)
        •      . . . . . . C.5.c.2
          Species of plants planted in riparian
          grass
        •      . . . . . . C.5.c.3 Acres planted in riparian .2
      •      . . C.6 Upland Habitat And Sediment ProjectY (Y/N)
        •      . . . . C.6.a Upland Habitat / Sediment Funding 22,568.00
        •      . . . . C.6.b.1 Acres of upland habitat area treated .1
        •      . . . . C.6.b.2 Miles of road treated in upland area 3.41
        •      . . . . C.6.c.1 Road drainage system improvements and reconstructionY (Y/N)
          •      . . . . . . C.6.c.2 Miles of road treated for drainage system improvements and reconstruction .10
        •      . . . . C.6.d.1 Road closure / abandonmentY (Y/N)
          •      . . . . . . C.6.d.2 Miles of road closed / abandoned .10
          •      . . . . . . C.6.d.3 Average width of road closed / abandoned6000 (Yards)
        •      . . . . C.6.f.1 Planting for erosion and sediment controlY (Y/N)
          •      . . . . . . C.6.f.2
            Species of plants planted for erosion and sediment control
            grasses