Description    


The project was completed as originally proposed, along with the addition of a new task with remaining funds. Specifically, the accomplishments were (1) We enhanced our current tool for web-based access to information of limiting factors and PCSRF projects and their locations by installing and configuring an interactive mapping component to our website, and using it to develop a pair of applications to deliver this information to public users. These applications are online and accessible at http://maps.critfc.org/. Users may view their area of interest and then show limiting factors to salmon and steelhead that were identified during subbasin planning, and may also view and query PCSRF-funded tribal restoration projects; (2) We performed an assessment of past Tribal PCSRF projects to compare them to limiting factors identified during subbasin planning. This assessment identified some of the challenges that exist in using automated approaches to link habitat actions and limiting factors, including the issue of differing results dependent on geographic scale. The report is available online at the CRITFC website technical reports page (http://www.critfc.org/tech/tech_rep.html); (3) We added a third task to design and implement an introductory GIS (Geographic Information Systems) course for CRITFC staff during the Winter of 2010. We conducted an orientation session with 12 particpants, and a set of following on-computer sessions for these participants to learn GIS basics. The course was helpful in orienting our staff on how to use GIS to view, analyze, and manage geographic information about salmon and their environment.

Project Benefit    


The target species are Spring Chinook, Summer Chinook, Fall Chinook, Coho, Winter Steelhead, and Summer Steelhead. Development of information on habitat improvements and evaluation of progress through past projects will help evaluate and direct future efforts to recover fish populations.

Accomplishments

Metric Completed Originally
Proposed

Funding Details

SourceFunds
PCSRF$37,869
Report Total:$37,869


Project Map



Worksites

CRITFC Office    


  • Worksite Identifier: CRITFC Office
  • Start Date:
  • End Date:
Area Description

No Area Description data was found for this worksite.

Location Information

  • Basin: Willamette (170900)
  • Subbasin: Lower Willamette
  • Watershed:
  • Subwatershed:
  • State: Oregon
  • Recovery Domain: Lower Columbia River
  • Latitude: 45.5288
  • Longitude: -122.6581

ESU

  • Upper Columbia River Spring-run Chinook Salmon ESU
  • Snake River Fall Chinook Salmon ESU
  • Lower Columbia River Chinook Salmon ESU
  • Mid-Columbia River Spring-run Chinook Salmon ESU
  • Upper Columbia River Summer- and Fall-run Chinook Salmon ESU
  • Deschutes River Summer/Fall-run Chinook Salmon ESU
  • Lower Columbia River Coho Salmon ESU
  • Upper Columbia River Steelhead DPS
  • Snake River Basin Steelhead DPS
  • Lower Columbia River Steelhead DPS
  • Middle Columbia River Steelhead DPS

Map

Photos

Metrics

Metrics
  • B.0 Salmonid Restoration Planning and AssessmentsY (Y/N)
    •      . . B.0.a Planning And Assessment Funding 37,869.00
    •      . . B.0.b.1 Area Encompassed 1,000.0
    •      . . B.2 Salmonid Habitat Assessment / InventoryY (Y/N)
      •      . . . . B.2.a Habitat Assessment Funding 37,869.00
      •      . . . . B.2.d Habitat surveysY (Y/N)
        •      . . . . . . B.2.d.1 Type of habitat survey/assessment (LOV)
        •      . . . . . . B.2.d.2 Amount of habitat assessed 100.0
        •      . . . . . . B.2.d.3 Amount of habitat assessed that needed restoration 50.0