Lower Mainstem Skokomish LWD - RM 5
Salmonid Habitat Restoration and Acquisition
|
16-1483 R | Puget Sound | 01/19/2018 | 12/31/2023 | 2018 | Completed | 01/14/2025 | |
| |
Description
The Skokomish River Mile 5 Habitat Restoration Project improved floodplain connectivity by installing 1 apex and 7 deflector engineered log jams; and creating 2,500 feet of side channel habitat with channel roughening logs between river miles 4.1 and 5.25. Chinook, Steelhead, Chum, Coho, Cutthroat and Bull Trout frequent this location and benefit from increased pool habitat with wood cover, and increased side channel rearing habitat. During flood events the side channel provide fish quiescent migration path between the Skokomish River, flooded wetlands and Purdy Creek to increase fish survival.
Project Benefit
Boost recovery salmonids supported by the Skokomish River into perpetuity. Improve instream habitat conditions and flood plain connection along River Mile 5 of the Skokomish River by installing large woody debris and creating side channel to enhance fish rearing, spawning and migration habitats.
Accomplishments
Instream Habitat |
Stream Miles Treated |
.75 |
.75 |
Funding Details |
PCSRF | $452,350 |
State | $20,523 |
Other | $150,643 |
Report Total: | $623,517 |
|
| |
Worksites
1-Lower Mainstem Skokomish Ri
- Worksite Identifier: 1-Lower Mainstem Skokomish Ri
- Start Date:
- End Date:
Area Description
No Area Description data was found for this worksite.
Location Information
- Basin: Puget Sound (171100)
- Subbasin: Skokomish (17110017)
- Watershed: Skokomish River-Frontal Hood Canal (1711001702)
- Subwatershed: Skokomish River-Frontal Hood Canal (171100170204)
- State: Washington
- Recovery Domain: Puget Sound
- Latitude: 47.30965335
- Longitude: -123.17603723
ESU
- Puget Sound/Strait of Georgia Coho Salmon ESU
- Hood Canal Summer-run Chum Salmon ESU
- Odd-year
- Un-Named ESU Chum
- Puget Sound Steelhead DPS
- Puget Sound Chinook Salmon ESU
Map
Photos
Metrics
Metrics
- C.0
Salmonid Habitat Restoration and AcquisitionY (Y/N)
- . . C.0.a
Habitat restoration and acquisition funding 623,516.68
- . . C.0.b
Length of stream treated/protected .75
- . . C.0.c
Project identified in a Plan or Watershed Assessment | |
|
- . . C.0.d.1
Project Monitoring (LOV)
- . . C.0.d.2
Monitoring Location (LOV)
- . . C.4
Instream Habitat ProjectY (Y/N)
- . . . . C.4.a
Instream Habitat Funding 623,516.68
- . . . . C.4.b
Total length of instream habitat treated .75
- . . . . C.4.c.1
Channel reconfiguration and connectivityY (Y/N)
- . . . . . . C.4.c.2
Type of change to channel configuration and connectivity (LOV)
- . . . . . . C.4.c.3
Miles of stream treated for channel reconfiguration and connectivity .10
- . . . . . . C.4.c.4
Miles of off-channel stream created through channel reconfiguration and connectivity .44
- . . . . . . C.4.c.5
Acres of off-channel or floodplain connected through channel reconfiguration and connectivity .5
- . . . . . . C.4.c.6
Instream pools created/added through channel reconfiguration and connectivity 0
- . . . . C.4.d.1
Channel structure placementY (Y/N)
- . . . . . . C.4.d.2
Material used for channel structure (LOV)
- . . . . . . C.4.d.3
Miles of stream treated through channel structure placement .75
- . . . . . . C.4.d.5
Pools expected to be created through channel structure placement 6
- . . . . . . C.4.d.7
Number of structures placed in channel 8
|
|