Sweetwater Creek Passage Assessment

Salmonid Restoration Planning and Assessments

Restoration Planning And Coordination
Project ID23-NezP-04
Recovery Domains -
Start Date03/01/2024
End Date08/31/2025
Year2023
StatusNew
Last Edited03/20/2024
 
1 - 1

Description    


This project targets the Lower Mainstem Clearwater River population of ESA listed Snake River A-run steelhead and the designated critical habitat, reintroduced Spring Chinook and Coho, and native fish within the Sweetwater Creek watershed. There are five bridges and two fords located along 1.2 miles of designated critical habitat and affecting 31.0 acres of riparian habitat. Project outcome is an assessment and designs on two fords and five bridges, which focuses on increased quality and quantity of instream habitat, improved stream process of flood conveyance, floodplain and side channel engagement, and sediment transport through new bridge designs, ford removal, stream crossing reduction, and improved floodplain access. Removing fords would be the highest priority, followed by upsizing of as many as 5 bridges to provide adequate passage, flow, and transport through the reach. This first phase will prioritize crossings to be removed, improved, or combined. Once this determination is established, any residual funding will be used to develop designs for crossings that will remain for improvements/combinations, or restoration designs on crossings to be removed. The second phase will consist of design/engineering and NEPA compliance. The final phase will be construction of improved crossings and/or stream restoration.



This project addresses 3 of the 6 limiting factors for the Lapwai Creek Watershed (habitat diversity, sedimentation, and passage) which were identified in the Lapwai Creek Ecological Restoration Strategy(LCERS), developed in conjunction between the Nez Perce Tribe, Nez Perce Soil and Water Conservation District, and other private & public stakeholders within the watershed. This project falls within Sweetwater Creek Reach 1. Sweetwater Creek Reach 1 was the second highest ranking assessment unit in 2009 when the LCERS was developed even though surface diversions reduced streamflow by almost 100%. Currently, the Tribe is involved in the Lewiston Orchards Project Water Exchange and Title Transfer Project (LOP) which is reducing the surface diversions to increase streamflow to the Sweetwater Creek watershed. Prior to 2006 summer base flows were reduced to 0.0 cfs. The 2020 Biological Assessment proposes base flows with up to 12.5 cfs. These increased stream flows along with the with this proposed project will restore, provide access to, and increase the amount designated critical habitat within Sweetwater Creek.



Project anticipates analysis of stream crossings in relation to types of access, types of crossing (fords, bridges, etc.) redundancy, land ownership, rights-of-way, easements, and condition. Upon completion of analysis, crossings selected for removal, improvement, or habitat restoration will be assigned a ranking based on landowner participation and funding, overall habitat improvement, and cost of project.



Outcomes of this project would be able to address a multitude of factors inadequate or excessive crossings affecting passage and designated critical habitat through the reach. Undersized crossings could be upsized to allow proper flow regimes and prevent upstream aggradation and downstream degradation of spawning and rearing habitat. Agricultural fords could be replaced with proper bridges or culverts, specifically addressing artificial substrate modification, increases in sediment, and elevation passage issues. Redundant crossings could be removed and adjacent riparian habitat restored.



Worksite #1 Lower Sweetwater Creek RM 2.3-3.5:

Propose to develop an assessment of complex of stream crossings consisting of fords and bridges, which are currently causing passage and stranding issues for ESA-species and repeated flooding, aggradation, and degradation. Propose to use remaining funds to produce designs for preferred assessment options.

Project Benefit    


Expected benefits of analysis include designs to reduce the number and effects of stream crossings. Improved and reduced stream crossings along with consequent implementation of designs would improve quantity and quality of designated critical habitat for ESA-listed Steelhead along with reintroduced Spring & Fall Chinook and Coho Salmon.

Accomplishments

Metric Completed Originally
Proposed

Funding Details

No Funding data has been entered for this project.


Project Map



Worksites

Lower Sweetwater Creek RM 2.3-3.5    


  • Worksite Identifier: Lower Sweetwater Creek RM 2.3-3.5
  • Start Date: 03/01/2024
  • End Date: 08/31/2025
Area Description

No Area Description data was found for this worksite.

Location Information

  • Basin:
  • Subbasin:
  • Watershed:
  • Subwatershed:
  • State:
  • Recovery Domain:
  • Latitude: 46.351
  • Longitude: -116.8257

ESU

  • Snake River Basin Steelhead DPS

Map

Photos

Metrics

Metrics
  • B.0 Salmonid Restoration Planning and AssessmentsY (Y/N)
    •      . . B.0.a Planning And Assessment Funding .00
    •      . . B.0.b.1 Area Encompassed
    •      . . B.0.b.2 Stream Miles Affected
    •      . . B.1 Restoration Planning And CoordinationY (Y/N)
      •      . . . . B.1.a Planning and Coordination funding
      •      . . . . B.1.b.11 Engineering/design work for restoration projectsY (Y/N)
        •      . . . . . . B.1.b.11.a
          Name of plan implemented
        •      . . . . . . B.1.b.11.b
          Description and scope of the plan implemented