Last Dam: Restoring steelhead rearing habitat through barrier removal on Upper Stuart Creek, Sonoma County.

Salmonid Restoration Planning and Assessments

Restoration Planning And Coordination
Project ID1678300472350
Recovery DomainsN Central California Coast
Start Date04/26/2023
End Date07/01/2024
Year2020
StatusOngoing
Last Edited05/03/2024
 
1 - 1

Description    


The project will produce design documents to removal of last barrier to fish passage on Stuart Creek, a tributary to Sonoma Creek with important steelhead rearing potential. The barrier, an aging 45-foot cement dam, presents a velocity and height barrier to refuge pools for juvenile salmonids. The dam will be replaced by an engineered boulder shoot system designed to accommodate passage to cool pools and historical rearing habitat above the dam site.

Project Benefit    


Ryan Watanabe, CDFW Environmental Scientist, has informed us that the Department supports removing Bouverie Dam with the intention of improving climate resiliency and fish migration, particularly in areas subjected to drought-related habitat fragmentation. Inflow sediment improvements will benefit recent downstream restoration actions for spawning habitat.

Accomplishments

Metric Completed Originally
Proposed

Funding Details

SourceFunds
PCSRF$110,189
In-Kind Donated Labor$40,000
Report Total:$150,189


Project Map



Worksites

1678300472697    


  • Worksite Identifier: 1678300472697
  • Start Date:
  • End Date:
Area Description
Upper Stuart Creek

Location Information

  • Basin:
  • Subbasin:
  • Watershed:
  • Subwatershed:
  • State: California
  • Recovery Domain: N Central California Coast
  • Latitude: 38.368824
  • Longitude: -122.4987

ESU

  • Central California Coast Steelhead DPS
  • Central California Coast Coho Salmon ESU

Map

Photos

Metrics

Metrics
  • B.0 Salmonid Restoration Planning and AssessmentsY (Y/N)
    •      . . B.0.a Planning And Assessment Funding .00
    •      . . B.0.b.1 Area Encompassed
    •      . . B.0.b.2 Stream Miles Affected
    •      . . B.1 Restoration Planning And CoordinationY (Y/N)
      •      . . . . B.1.a Planning and Coordination funding
      •      . . . . B.1.b.11 Engineering/design work for restoration projectsY (Y/N)
        •      . . . . . . B.1.b.11.a
          Name of plan implemented
        •      . . . . . . B.1.b.11.b
          Description and scope of the plan implemented