Albion River and Tom Bell Creek Instream Habitat Enhancement Project
Salmonid Habitat Restoration and Acquisition
|
| 1640903380173 | | - | | 04/22/2022 | | 03/27/2026 | | 2021 | | Completed | | 04/07/2026 | | |
| |
Description
The grantee, Trout Unlimited, had California Conservation Corps install a total of 43 instream features within 0.9mi of river - 0.3mi on the mainstem Albion River and 0.6mi on its tributary, Tom Bell Creek. On the Albion River, 15 large wood features were installed (consisting of 53 pieces of large wood), and on the Tom Bell Creek, 28 large wood features were installed (consisting of 76 pieces of large wood). Available native slash and small woody debris were installed into structures to provide immediate cover for salmonids and encourage floating debris accumulation/aggradation where beneficial.
All FY18 PCSRF funds were spent within the award period.
Project Benefit
This project will increase stream habitat complexity, pool frequency, pool depth, high-flow refugia, and over-summer rearing habitat for Coho Salmon, Steelhead Trout, and Chinook Salmon.
Accomplishments
| Instream Habitat |
| Stream Miles Treated |
.90 |
.90 |
Funding Details |
| PCSRF | $335,493 |
| In-Kind Donated Labor | $113,184 |
| In-Kind Other | $94,200 |
| Report Total: | $542,877 |
|
| |
Worksites
1640903380422
- Worksite Identifier: 1640903380422
- Start Date:
- End Date:
Area Description
Albion River and Tom Bell Creek
Location Information
- Basin:
- Subbasin:
- Watershed:
- Subwatershed:
- State:
- Recovery Domain:
- Latitude: 39.26691
- Longitude: -123.64361
ESU
- California Coastal Chinook Salmon ESU
- Central California Coast Coho Salmon ESU
- Northern California Steelhead DPS
Map
Photos
Metrics
Metrics
- C.0
Salmonid Habitat Restoration and AcquisitionY (Y/N)
- . . C.0.a
Habitat restoration and acquisition funding 542,877.00
- . . C.0.b
Length of stream treated/protected .90
- . . C.0.c
| Project identified in a Plan or Watershed Assessment | |
|
- . . C.0.d.1
Project Monitoring (LOV)
- . . C.0.d.2
Monitoring Location (LOV)
- . . C.4
Instream Habitat ProjectY (Y/N)
- . . . . C.4.a
Instream Habitat Funding 542,876.96
- . . . . C.4.b
Total length of instream habitat treated .90
- . . . . C.4.d.1
Channel structure placementY (Y/N)
- . . . . . . C.4.d.2
Material used for channel structure (LOV)
- . . . . . . C.4.d.3
Miles of stream treated through channel structure placement .90
- . . . . . . C.4.d.5
Pools expected to be created through channel structure placement 12
- . . . . . . C.4.d.7
Number of structures placed in channel 43
|
|