Coquille Instream 2007

Salmonid Habitat Restoration and Acquisition

Instream Habitat
Project IDOWEB 207-286-5545
Recovery Domains -
Start Date08/30/2007
End Date12/10/2009
Year2006
StatusCompleted
Last Edited04/12/2024
 
1 - 1

Description    


This project excavated or blasted a pool; installed a log and rock/boulder flow deflector; installed a log flow deflector; installed a rock/boulder flow deflector; installed a rock/boulder V structure; modified or created a main stream channel; placed boulders instream; placed instream anchored habitat structures; placed large wood instream; reconnected side channels to the stream, or improved access to side channels.

Project Benefit    


OWRI: improve/increase stream gravel recruitment; improve/increase stream interaction with floodplain; improve/increase stream over-winter habitat; improve/increase stream pools; improve/increase stream rearing habitat; improve/increase stream spawning habitat; improve/increase stream structure & complexity; improve/increase stream summer habitat;

Accomplishments

Metric Completed Originally
Proposed
Instream Habitat
  Stream Miles Treated 1.65

Funding Details

SourceFunds
State$77,093
Other$36,500
In-Kind Other$4,000
Report Total:$117,593


Project Map



Worksites

20090314    


  • Worksite Identifier: 20090314
  • Start Date:
  • End Date:
Area Description

No Area Description data was found for this worksite.

Location Information

  • Basin:
  • Subbasin:
  • Watershed:
  • Subwatershed:
  • State:
  • Recovery Domain:
  • Latitude: 42.75155858
  • Longitude: -124.10128943

ESU

  • Lower Columbia River Coho Salmon ESU
  • Oregon Coast Steelhead DPS

Map

Photos

Metrics

Metrics
  • C.0 Salmonid Habitat Restoration and AcquisitionY (Y/N)
    •      . . C.0.a Habitat restoration and acquisition funding 70,971.78
    •      . . C.0.b Length of stream treated/protected .80
    •      . . C.0.c
      Project identified in a Plan or Watershed Assessment
      Coquille Subbasin Plan 2007/2007/Coquille Tribe
    •      . . C.0.d.1 Project Monitoring (LOV)
    •      . . C.0.d.2 Monitoring Location (LOV)
    •      . . C.4 Instream Habitat ProjectY (Y/N)
      •      . . . . C.4.a Instream Habitat Funding 70,971.78
      •      . . . . C.4.b Total length of instream habitat treated .80
      •      . . . . C.4.c.1 Channel reconfiguration and connectivityY (Y/N)
        •      . . . . . . C.4.c.2 Type of change to channel configuration and connectivity (LOV)
        •      . . . . . . C.4.c.3 Miles of stream treated for channel reconfiguration and connectivity .01
        •      . . . . . . C.4.c.4 Miles of off-channel stream created through channel reconfiguration and connectivity .03
        •      . . . . . . C.4.c.6 Instream pools created/added through channel reconfiguration and connectivity 4
      •      . . . . C.4.d.1 Channel structure placementY (Y/N)
        •      . . . . . . C.4.d.2 Material used for channel structure (LOV)
        •      . . . . . . C.4.d.3 Miles of stream treated through channel structure placement .80
        •      . . . . . . C.4.d.7 Number of structures placed in channel 54

20090315    


  • Worksite Identifier: 20090315
  • Start Date:
  • End Date:
Area Description

No Area Description data was found for this worksite.

Location Information

  • Basin:
  • Subbasin:
  • Watershed:
  • Subwatershed:
  • State:
  • Recovery Domain:
  • Latitude: 42.97484997
  • Longitude: -124.00615817

ESU

  • Lower Columbia River Coho Salmon ESU
  • Oregon Coast Steelhead DPS

Map

Photos

Metrics

Metrics
  • C.0 Salmonid Habitat Restoration and AcquisitionY (Y/N)
    •      . . C.0.a Habitat restoration and acquisition funding 17,488.81
    •      . . C.0.b Length of stream treated/protected .25
    •      . . C.0.c
      Project identified in a Plan or Watershed Assessment
      Coquille Subbasin Plan 2007/2007/Coquille Tribe
    •      . . C.0.d.1 Project Monitoring (LOV)
    •      . . C.0.d.2 Monitoring Location (LOV)
    •      . . C.4 Instream Habitat ProjectY (Y/N)
      •      . . . . C.4.a Instream Habitat Funding 17,488.81
      •      . . . . C.4.b Total length of instream habitat treated .25
      •      . . . . C.4.d.1 Channel structure placementY (Y/N)
        •      . . . . . . C.4.d.2 Material used for channel structure (LOV)
        •      . . . . . . C.4.d.3 Miles of stream treated through channel structure placement .25
        •      . . . . . . C.4.d.7 Number of structures placed in channel 85

20070531    


  • Worksite Identifier: 20070531
  • Start Date:
  • End Date:
Area Description

No Area Description data was found for this worksite.

Location Information

  • Basin:
  • Subbasin:
  • Watershed:
  • Subwatershed:
  • State:
  • Recovery Domain:
  • Latitude: 42.75168397
  • Longitude: -124.09644742

ESU

  • Lower Columbia River Coho Salmon ESU
  • Oregon Coast Steelhead DPS

Map

Photos

Metrics

Metrics
  • C.0 Salmonid Habitat Restoration and AcquisitionY (Y/N)
    •      . . C.0.a Habitat restoration and acquisition funding 29,132.17
    •      . . C.0.b Length of stream treated/protected .60
    •      . . C.0.c
      Project identified in a Plan or Watershed Assessment
      South Fork Coquille Watershed Analysis/1996/USFS
    •      . . C.0.d.1 Project Monitoring (LOV)
    •      . . C.0.d.2 Monitoring Location (LOV)
    •      . . C.4 Instream Habitat ProjectY (Y/N)
      •      . . . . C.4.a Instream Habitat Funding 29,132.17
      •      . . . . C.4.b Total length of instream habitat treated .60
      •      . . . . C.4.c.1 Channel reconfiguration and connectivityY (Y/N)
        •      . . . . . . C.4.c.2 Type of change to channel configuration and connectivity (LOV)
        •      . . . . . . C.4.c.3 Miles of stream treated for channel reconfiguration and connectivity .01
        •      . . . . . . C.4.c.4 Miles of off-channel stream created through channel reconfiguration and connectivity .06
        •      . . . . . . C.4.c.6 Instream pools created/added through channel reconfiguration and connectivity 0
      •      . . . . C.4.d.1 Channel structure placementY (Y/N)
        •      . . . . . . C.4.d.2 Material used for channel structure (LOV)
        •      . . . . . . C.4.d.3 Miles of stream treated through channel structure placement .60
        •      . . . . . . C.4.d.7 Number of structures placed in channel 21