McKenzie Canyon Black Butte/Association Canals Pipeline - Phase III & IV

Salmonid Habitat Restoration and Acquisition

Upland Habitat And Sediment
Project IDOWEB 207-105-5207
Recovery Domains -
Start Date05/29/2007
End Date07/20/2009
Year2006
StatusCompleted
Last Edited04/12/2024
 
1 - 1

Description    


This project improved an irrigation system.

Project Benefit    


OWRI: decrease stream temperature; improve/increase stream flow; increase/improve water conservation;

Accomplishments

Metric Completed Originally
Proposed
Upland Habitat
  Acres Treated 2,000.0

Funding Details

SourceFunds
State$299,722
Other$952,085
In-Kind Other$841,382
Report Total:$2,093,189


Project Map



Worksites

20090019    


  • Worksite Identifier: 20090019
  • Start Date:
  • End Date:
Area Description

No Area Description data was found for this worksite.

Location Information

  • Basin:
  • Subbasin:
  • Watershed:
  • Subwatershed:
  • State:
  • Recovery Domain:
  • Latitude: 44.25821664
  • Longitude: -121.52297493

ESU

  • Middle Columbia River Steelhead DPS

Map

Photos

Metrics

Metrics
  • C.0 Salmonid Habitat Restoration and AcquisitionY (Y/N)
    •      . . C.0.a Habitat restoration and acquisition funding 2,093,188.73
    •      . . C.0.b Length of stream treated/protected .00
    •      . . C.0.c
      Project identified in a Plan or Watershed Assessment
      2004 Deschutes Subbasin Plan/2004/Northwest Power and Conservation Council
    •      . . C.0.d.1 Project Monitoring (LOV)
    •      . . C.0.d.2 Monitoring Location (LOV)
    •      . . C.6 Upland Habitat And Sediment ProjectY (Y/N)
      •      . . . . C.6.a Upland Habitat / Sediment Funding 2,093,188.73
      •      . . . . C.6.b.1 Acres of upland habitat area treated 2,000.0
      •      . . . . C.6.i.1 Upland agriculture managementY (Y/N)
        •      . . . . . . C.6.i.2 Upland agriculture management action(s) taken (LOV)
        •      . . . . . . C.6.i.3 Upland acres managed for agriculture 2,000.0