Big River Salmonid Rearing Habitat and Large Wood Enhancement Project Designs.

Salmonid Restoration Planning and Assessments

Restoration Planning And Coordination
Project ID1611968186709
Recovery DomainsN Central California Coast
Start Date05/25/2021
End Date03/07/2023
Year2019
StatusTerminated
Last Edited03/12/2024
 
1 - 1

Description    


Due to the AB1757 and associated landowner carbon offset sales and its potential implications for The Conservation Fund has decided to forego any CA state grant funding agreements or reimbursements until the issue has been further clarified. The Grantee TU has made an effort to find a solution to move forward. They will continue with the design project and the landowner will pay for the costs. CDFW engineering and fisheries staff will stay involved.

Project Benefit    


The project goal is to restore salmonid habitat complexity in a three-mile reach of the Big River by installing moderate to large-scale ELJ structures. These structures will be used to create habitat diversity and flow complexity for Coho, steelhead, and Chinook Salmon to improve both summer and winter rearing conditions. It is expected that the habitat improvements will also benefit lamprey, and other native aquatic species.

Accomplishments

Metric Completed Originally
Proposed

Funding Details

SourceFunds
PCSRF$95,252
Report Total:$95,252


Project Map



Worksites

1611968186939    


  • Worksite Identifier: 1611968186939
  • Start Date:
  • End Date:
Area Description
Big River Project Reach

Location Information

  • Basin: Northern California Coastal (180101)
  • Subbasin: Big-Navarro-Garcia (18010108)
  • Watershed: Big River (1801010803)
  • Subwatershed: Lower Big River (180101080304)
  • State: California
  • Recovery Domain: N Central California Coast
  • Latitude: 39.31183
  • Longitude: -123.63774

ESU

  • California Coastal Chinook Salmon ESU
  • Central California Coast Coho Salmon ESU
  • Northern California Steelhead DPS

Map

Photos

Metrics

Metrics
  • B.0 Salmonid Restoration Planning and AssessmentsY (Y/N)
    •      . . B.0.a Planning And Assessment Funding 34,689.00
    •      . . B.0.b.1 Area Encompassed .0
    •      . . B.0.b.2 Stream Miles Affected .00
    •      . . B.1 Restoration Planning And CoordinationY (Y/N)
      •      . . . . B.1.a Planning and Coordination funding 34,688.92
      •      . . . . B.1.b.11 Engineering/design work for restoration projectsY (Y/N)
        •      . . . . . . B.1.b.11.a
          Name of plan implemented
          None - project was terminated
        •      . . . . . . B.1.b.11.b
          Description and scope of the plan implemented
          None - project was terminated