Meyer Gulch Fish Passage Design Project

Salmonid Restoration Planning and Assessments

Restoration Planning And Coordination
Project ID1578345251958
Recovery DomainsN Central California Coast
Start Date04/01/2020
End Date05/10/2023
Year2019
StatusCompleted
Last Edited02/27/2024
 
1 - 1

Description    


Engineer designs were developed to 100% for a pool-chute fish passage feature on Meyer Gulch. The feature will pass all salmonids at all life stages. The design is not fundable or permittable for implementation by FRGP but is a typical design that CDFW and NOAA permit and it can be funded through other means.

Project Benefit    


This project will address impediments to adult and juvenile fish passage to 0.75 miles of upstream habitat in Meyer Gulch. The existing culvert likely poses a temporal migration barrier to all life stages of steelhead trout. This project will produce final engineered designs to replace the existing culvert with a new structure that adheres to CDFW and NMFS passage guidelines.

Accomplishments

Metric Completed Originally
Proposed

Funding Details

SourceFunds
PCSRF$65,954
Other$39,382
Report Total:$105,336


Project Map



Worksites

1578345252162    


  • Worksite Identifier: 1578345252162
  • Start Date:
  • End Date:
Area Description
Meyer Gulch crossing at Holmes Ranch Road

Location Information

  • Basin: Northern California Coastal (180101)
  • Subbasin: Big-Navarro-Garcia (18010108)
  • Watershed: Navarro River (1801010804)
  • Subwatershed: Upper Navarro River (180101080408)
  • State: California
  • Recovery Domain: N Central California Coast
  • Latitude: 39.12483
  • Longitude: -123.50724

ESU

  • California Coastal Chinook Salmon ESU
  • Central California Coast Coho Salmon ESU
  • Northern California Steelhead DPS

Map

Photos

Metrics

Metrics
  • B.0 Salmonid Restoration Planning and AssessmentsY (Y/N)
    •      . . B.0.a Planning And Assessment Funding 105,336.00
    •      . . B.0.b.1 Area Encompassed 58.0
    •      . . B.0.b.2 Stream Miles Affected .75
    •      . . B.1 Restoration Planning And CoordinationY (Y/N)
      •      . . . . B.1.a Planning and Coordination funding 105,336.00
      •      . . . . B.1.b.11 Engineering/design work for restoration projectsY (Y/N)
        •      . . . . . . B.1.b.11.a
          Name of plan implemented
          NOAA, Oct 2016, Final Coastal Multispecies Recovery Plan for California Coastal Chinook Salmon, Northern California Steelhead and Central California Coast Steelhead, NOAA
        •      . . . . . . B.1.b.11.b
          Description and scope of the plan implemented
          Designed made that addressed task NvroR-NCSW-5.1.1.1 by improving passage to upstream habitat.