Asotin Creek PA 3.2 Design

Salmonid Restoration Planning and Assessments

Restoration Planning And Coordination
Project ID22-1009 P
Recovery Domains -
Start Date09/22/2022
End Date03/15/2025
Year2022
StatusOngoing
Last Edited04/12/2024
 
1 - 1

Description    


The Asotin County Conservation District is sponsoring the Asotin Creek Project Area (PA) 3.2 Design project to develop a final design report, ready to construct engineering plans, and complete environmental compliance including permit and cultural resource requirements.This project targets a 1.2 mile segment of PA 3. The conceptual plan for PA 3.2 includes controlling invasive vegetation encroachment and add large woody debris to increase complexity. The project is located south of the City of Asotin, WA along Asotin Creek Road. Asotin Creek flows directly into the Snake River. The project begins at river mile (RM) 4.0 and ends are RM 5.2. The priority species that will benefit from the project, once implemented, is steelhead but will also support fall chinook, spring chinook and bull trout.

Project Benefit    


The goal of this project is to provide instream habitat complexity through the placement of large wood structures, to enhance habitat for Snake River steelhead for all life stages, control invasive vegetation encroachment, and promote riparian function.

Accomplishments

Metric Completed Originally
Proposed

Funding Details

SourceFunds
PCSRF$84,000
Other$21,000
Report Total:$105,000


Project Map



Worksites

1-Asotin Creek PA 3.2 Design    


  • Worksite Identifier: 1-Asotin Creek PA 3.2 Design
  • Start Date:
  • End Date:
Area Description

No Area Description data was found for this worksite.

Location Information

  • Basin:
  • Subbasin:
  • Watershed:
  • Subwatershed:
  • State:
  • Recovery Domain:
  • Latitude: 46.32198215
  • Longitude: -117.12563774

ESU

  • Snake River Basin Steelhead DPS
  • Un-Named ESU Chinook
  • Snake River Spring/Summer-run Chinook Salmon ESU

Map

Photos

Metrics

Metrics
  • B.0 Salmonid Restoration Planning and AssessmentsY (Y/N)
    •      . . B.0.a Planning And Assessment Funding
    •      . . B.0.b.1 Area Encompassed
    •      . . B.0.b.2 Stream Miles Affected
    •      . . B.1 Restoration Planning And CoordinationY (Y/N)
      •      . . . . B.1.a Planning and Coordination funding
      •      . . . . B.1.b.11 Engineering/design work for restoration projectsY (Y/N)
        •      . . . . . . B.1.b.11.a
          Name of plan implemented
        •      . . . . . . B.1.b.11.b
          Description and scope of the plan implemented