Albion River Coho Habitat Enhancement Project - Large Wood Installation

Salmonid Habitat Restoration and Acquisition

Instream Habitat
Project ID1578343461659
Recovery DomainsN Central California Coast
Start Date05/15/2020
End Date11/29/2022
Year2019
StatusCompleted
Last Edited02/27/2024
 
1 - 1

Description    


A total of 20 instream features were installed in 0.69mi of Albion River, consisting of 64 LW pieces. During construction, project designs were modified with CDFW approval. 1 feature was added in the project reach with CDFW approval due to a lack of material quality at several other features. The proposed number of logs for these features were installed at the added feature and in other locations in the project reach. Various CDFW approved anchoring techniques were used to hold multiple logs together to form complex structures including wedging logs into existing live mature trees growing on riparian banks and anchoring to live trees with hardware. Available native slash & small woody debris were installed into structures to provide immediate cover for salmonids and encourage floating debris accumulation & aggradation where needed. All FY16 PCSRF funds were spent within the award period (even though the project ended outside the FY16 award period).

Project Benefit    


The addition of these structures will enhance spawning and rearing habitats by providing cover, increasing pool depth, frequency and complexity, sorting and collecting spawning gravels, and by providing velocity refuge during peak winter flows for juvenile salmonids and migrating adult salmonids.

Accomplishments

Metric Completed Originally
Proposed
Instream Habitat
  Stream Miles Treated .69 .69

Funding Details

SourceFunds
PCSRF$158,327
In-Kind Donated Labor$40,358
In-Kind Other$62,510
Report Total:$261,195


Project Map



Worksites

1578343461865    


  • Worksite Identifier: 1578343461865
  • Start Date:
  • End Date:
Area Description
Albion River

Location Information

  • Basin: Northern California Coastal (180101)
  • Subbasin: Big-Navarro-Garcia (18010108)
  • Watershed: Albion River-Frontal Pacific Ocean (1801010808)
  • Subwatershed: Albion River (180101080801)
  • State: California
  • Recovery Domain: N Central California Coast
  • Latitude: 39.26878
  • Longitude: -123.63754

ESU

  • California Coastal Chinook Salmon ESU
  • Central California Coast Coho Salmon ESU
  • Northern California Steelhead DPS

Map

Photos

Metrics

Metrics
  • C.0 Salmonid Habitat Restoration and AcquisitionY (Y/N)
    •      . . C.0.a Habitat restoration and acquisition funding 261,195.00
    •      . . C.0.b Length of stream treated/protected .69
    •      . . C.0.c
      Project identified in a Plan or Watershed Assessment
      NOAA, Sept 2012, Recovery Plan for Central CA Coast Coho Salmon
    •      . . C.0.d.1 Project Monitoring (LOV)
    •      . . C.0.d.2 Monitoring Location (LOV)
    •      . . C.4 Instream Habitat ProjectY (Y/N)
      •      . . . . C.4.a Instream Habitat Funding 261,195.25
      •      . . . . C.4.b Total length of instream habitat treated .69
      •      . . . . C.4.d.1 Channel structure placementY (Y/N)
        •      . . . . . . C.4.d.2 Material used for channel structure (LOV)
        •      . . . . . . C.4.d.3 Miles of stream treated through channel structure placement .69
        •      . . . . . . C.4.d.4 Acres of streambed treated through channel structure placement 1.9
        •      . . . . . . C.4.d.5 Pools expected to be created through channel structure placement 0
        •      . . . . . . C.4.d.6 Yards of average stream-width at mid-point of channel structure placement project7 (Yards)
        •      . . . . . . C.4.d.7 Number of structures placed in channel 20