Dosewallips Floodplain & Estuary Restoration 2016

Salmonid Habitat Restoration and Acquisition

Instream Habitat Riparian Habitat
Project ID16-1482 R
Recovery Domains -
Start Date12/08/2016
End Date03/15/2022
Year2016
StatusCompleted
Last Edited04/12/2024
 
1 - 1

Description    


The Lower Dosewallips Floodplain and Estuary Restoration was completed in the spring of 2022, main project construction occurred in the summer of 2021, with planting in the fall and invasive removal and touch up planting occurring in Spring 2022. The main project construction resulted in the removal of: 1000 ft of revetment along the main river shoreline, and the removal 2820 linear feet of asphalt roads in the floodplain, including 500 feet of road that was buried 2 feet underneath the existing surface and was likely abandoned by parks after a flood buried it in the 1960s or 1970s. We also created over 3500 feet of new distributary channel and constructed 3 engineered log jams at distributary junctions with the main river. Iinvasive species (Himalayan blackberry) were removed on 2 acres and riparian plantings occurred throughout the entire area disturbed by construction. 

Project Benefit    


The goal of this project was to restore natural floodplain processes to 4.25 acres of tidal floodplain in the Lower Dosewallips River. This wa accomplished through the removal of over 1000 feet of revetment within the project reach, as well as 2800 feet of asphalt road. This allowed for the creation of 3500 feet of new distributary channels within the old campground footprint. We also added three new ELJs to the mainstem of the river at distributary junctions. 

Accomplishments

Metric Completed Originally
Proposed
Instream Habitat
  Stream Miles Treated .30 .30
Estuarine Habitat
  Acres Created
  Acres Treated .4 .4
Riparian Habitat
  Stream Miles Treated .50 .50
  Acres Treated 5.5 5.5

Funding Details

SourceFunds
PCSRF$374,478
Other$370,763
Report Total:$745,241


Project Map



Worksites

1-Dosewallips State Park    


  • Worksite Identifier: 1-Dosewallips State Park
  • Start Date:
  • End Date:
Area Description

No Area Description data was found for this worksite.

Location Information

  • Basin:
  • Subbasin:
  • Watershed:
  • Subwatershed:
  • State:
  • Recovery Domain:
  • Latitude: 47.68742838
  • Longitude: -122.89909132

ESU

  • Puget Sound/Strait of Georgia Coho Salmon ESU
  • Hood Canal Summer-run Chum Salmon ESU
  • Puget Sound Steelhead DPS
  • Puget Sound Chinook Salmon ESU

Map

Photos

Metrics

Metrics
  • C.0 Salmonid Habitat Restoration and AcquisitionY (Y/N)
    •      . . C.0.a Habitat restoration and acquisition funding 745,240.76
    •      . . C.0.b Length of stream treated/protected .30
    •      . . C.0.c
      Project identified in a Plan or Watershed Assessment
    •      . . C.0.d.1 Project Monitoring (LOV)
    •      . . C.0.d.2 Monitoring Location (LOV)
    •      . . C.4 Instream Habitat ProjectY (Y/N)
      •      . . . . C.4.a Instream Habitat Funding 704,735.88
      •      . . . . C.4.b Total length of instream habitat treated .30
      •      . . . . C.4.c.1 Channel reconfiguration and connectivityY (Y/N)
        •      . . . . . . C.4.c.2 Type of change to channel configuration and connectivity (LOV)
        •      . . . . . . C.4.c.3 Miles of stream treated for channel reconfiguration and connectivity .20
        •      . . . . . . C.4.c.4 Miles of off-channel stream created through channel reconfiguration and connectivity .66
        •      . . . . . . C.4.c.5 Acres of off-channel or floodplain connected through channel reconfiguration and connectivity 1.0
        •      . . . . . . C.4.c.6 Instream pools created/added through channel reconfiguration and connectivity 3
      •      . . . . C.4.d.1 Channel structure placementY (Y/N)
        •      . . . . . . C.4.d.2 Material used for channel structure (LOV)
        •      . . . . . . C.4.d.3 Miles of stream treated through channel structure placement .01
        •      . . . . . . C.4.d.5 Pools expected to be created through channel structure placement 3
        •      . . . . . . C.4.d.7 Number of structures placed in channel 3
      •      . . C.5 Riparian Habitat ProjectY (Y/N)
        •      . . . . C.5.a Riparian Habitat Funding 40,504.88
        •      . . . . C.5.b.1 Total riparian miles streambank treated .50
        •      . . . . C.5.b.2 Total Riparian Acres Treated 5.5
        •      . . . . C.5.c.1 Riparian plantingY (Y/N)
          •      . . . . . . C.5.c.2
            Species of plants planted in riparian
            Salix ssp  Picea sitchensis Thuja plicata  Pseudotsuga menzesii
          •      . . . . . . C.5.c.3 Acres planted in riparian 5.5
          •      . . . . . . C.5.c.4 Miles of streambank treated with riparian planting .40
        •      . . . . C.5.h.1 Riparian plant removal/controlY (Y/N)
          •      . . . . . . C.5.h.2
            Species of plants treated/removed in riparian
            Rubus discolor
          •      . . . . . . C.5.h.3 Acres of riparian treated for plant removal/control 1.0
          •      . . . . . . C.5.h.4 Miles of streambank treated for riparian plant removal/control .10
        •      . . C.9 Estuarine/Nearshore ProjectY (Y/N)
          •      . . . . C.9.a Estuarine/nearshore funding
          •      . . . . C.9.b Total amount of estuarine/nearshore area treated .4
          •      . . . . C.9.k.1 Shoreline armor removal or modificationY (Y/N)
            •      . . . . . . C.9.k.2 Miles of shoreline treated .30