Cachagua Creek Fish Passage Restoration Project - Valley Creek Park
Salmonid Habitat Restoration and Acquisition
|
725514 | S. California - S. Central CA Coast | 06/15/2018 | 08/12/2022 | 2018 | Completed | 01/25/2024 | |
| |
Description
This project removed the most downstream steelhead migration barrier in Cachagua Creek (a concrete automobile ford) and replaced it with a vented ford to allow full fish passage while insuring continued access to the Valley Creek Mobile Home Park. The vented ford installed consisted of 3 prefabricated concrete box culverts, each having a span of 24 feet long
by 12 feet high and provide a 20-foot roadway. The box culvert inverts were embedded below the channel grade and backfilled with native stream bed material to maintain a natural channel bottom that will provide passage opportunities similar to adjoining reaches of the channel. The stream was dry during construction, so no surface flow de-watering and no fish relocation was necessary. Final project resulted in 2.1 miles of stream made accessible to salmonid.
Overall stream length treated: 150 ft
Length of Aquatic habitat disturbed: 150 ft
Area of instream features installed within bankfull channel (square feet): 9,375 = 0.21 ac
Project Benefit
The removal of the concrete crossing and construction of a vented ford will provide fish passage salmonids.
Accomplishments
Fish Passage |
Barriers Removed |
|
|
Miles Opened |
2.10 |
10.40 |
Funding Details |
PCSRF | $1,028,221 |
In-Kind Donated Labor | $2,932 |
In-Kind Other | $257,575 |
Report Total: | $1,288,728 |
|
| |
Worksites
7211116
- Worksite Identifier: 7211116
- Start Date:
- End Date:
Area Description
existing concrete ford
Location Information
- Basin: Central California Coastal (180600)
- Subbasin: Central Coastal (18060006)
- Watershed: Carmel River (1806000601)
- Subwatershed: Cachagua Creek (180600060101)
- State: California
- Recovery Domain: S. California - S. Central CA Coast
- Latitude: 36.398778
- Longitude: -121.65251
ESU
- South-Central California Coast Steelhead DPS
Map
Photos
Metrics
Metrics
- C.0
Salmonid Habitat Restoration and AcquisitionY (Y/N)
- . . C.0.a
Habitat restoration and acquisition funding 1,288,728.00
- . . C.0.b
Length of stream treated/protected .03
- . . C.0.c
Project identified in a Plan or Watershed Assessment | |
|
- . . C.0.d.1
Project Monitoring (LOV)
- . . C.0.d.2
Monitoring Location (LOV)
- . . C.2
Fish Passage ImprovementY (Y/N)
- . . . . C.2.a
Fish Passage Funding 1,288,728.00
- . . . . C.2.b.1
Length of stream made accessible 2.10
- . . . . C.2.b.3
Type of blockage/barrier (LOV)
- . . . . C.2.b.4
Number of blockages/impediments/barriers impeding passage 1
- . . . . C.2.f.1
Culvert installed or improved at road stream crossingY (Y/N)
- . . . . . . C.2.f.2
Number of culverts installed or improved 1
- . . . . . . C.2.f.3
Miles of stream made accessible by culvert installation/upgrade 2.10
|
|