Cachagua Creek Fish Passage Restoration Project - Valley Creek Park

Salmonid Habitat Restoration and Acquisition

Fish Passage Improvement
Project ID725514
Recovery DomainsS. California - S. Central CA Coast
Start Date06/15/2018
End Date08/01/2022
Year2018
StatusOngoing
Last Edited04/11/2022
 
1 - 1

Description    


Remove existing concrete low flow crossing / ford on private property that is a migration barrier to the federally threatened South Central California Coast Steelhead on Cachagua Creek and replace it with a vented ford (3 box culverts) to provide fish passage and landowner access across the creek consistent with designs developed and approved thru 2015 FRGP Grant #P1540401. PCSRF FY2016 funds will be spent within the allowable award window.

Project Benefit    


The removal of the concrete crossing and construction of a vented ford will provide fish passage salmonids.

Accomplishments

Metric Completed Originally
Proposed
Fish Passage
  Barriers Removed
  Miles Opened 10.40

Funding Details

SourceFunds
PCSRF$1,034,231
Report Total:$1,034,231


Project Map



Worksites

7211116    


  • Worksite Identifier: 7211116
  • Start Date:
  • End Date:
Area Description
existing concrete ford

Location Information

  • Basin: Central California Coastal
  • Subbasin:
  • Watershed:
  • Subwatershed:
  • State: California
  • Recovery Domain: S. California - S. Central CA Coast
  • Latitude: 36.398778
  • Longitude: -121.65251

ESU

  • South-Central California Coast Steelhead DPS

Map

Photos

Metrics

Metrics
  • C.0 Salmonid Habitat Restoration and AcquisitionY (Y/N)
    •      . . C.0.a Habitat restoration and acquisition funding .00
    •      . . C.0.b Length of stream treated/protected
    •      . . C.0.c
      Project identified in a Plan or Watershed Assessment
    •      . . C.0.d.1 Project Monitoring (LOV)
    •      . . C.0.d.2 Monitoring Location (LOV)
    •      . . C.2 Fish Passage ImprovementY (Y/N)
      •      . . . . C.2.a Fish Passage Funding
      •      . . . . C.2.b.1 Length of stream made accessible
      •      . . . . C.2.b.3 Type of blockage/barrier (LOV)
      •      . . . . C.2.b.4 Number of blockages/impediments/barriers impeding passage
      •      . . . . C.2.f.1 Culvert installed or improved at road stream crossingY (Y/N)
        •      . . . . . . C.2.f.2 Number of culverts installed or improved
        •      . . . . . . C.2.f.3 Miles of stream made accessible by culvert installation/upgrade