James Creek Coho Stream Habitat Enhancement Project
Salmonid Habitat Restoration and Acquisition
|
725165 | N Central California Coast | 06/01/2017 | 01/13/2021 | 2016 | Completed | 01/25/2024 | |
| |
Description
28 features containing 93 pieces of properly sized LWD were installed in James Creek to improve the quality and quantity of spawning and rearing habitat for Coho and Steelhead on 0.88 miles of James Creek. All FY14 funds were spent within the appropriate award window.
Project Benefit
Spawning habitat and escape cover will be improved with additional large woody debris structures.
Accomplishments
Instream Habitat |
Stream Miles Treated |
.88 |
.14 |
Funding Details |
PCSRF | $173,133 |
In-Kind Donated Labor | $65,316 |
In-Kind Other | $46,230 |
Report Total: | $284,679 |
|
| |
Worksites
7211365
- Worksite Identifier: 7211365
- Start Date:
- End Date:
Area Description
James Creek
Location Information
- Basin: Northern California Coastal (180101)
- Subbasin: Big-Navarro-Garcia (18010108)
- Watershed: Big River (1801010803)
- Subwatershed:
- State: California
- Recovery Domain: N Central California Coast
- Latitude: 39.35285
- Longitude: -123.51032
ESU
- California Coastal Chinook Salmon ESU
- Northern California Steelhead DPS
- Central California Coast Coho Salmon ESU
Map
Photos
Metrics
Metrics
- C.0
Salmonid Habitat Restoration and AcquisitionY (Y/N)
- . . C.0.a
Habitat restoration and acquisition funding 284,680.00
- . . C.0.b
Length of stream treated/protected .88
- . . C.0.c
Project identified in a Plan or Watershed Assessment | |
Downie, S., B. deWaard, E. Dudik, D. McGuire, and R. Rutland. 2006. Big River Basin
Assessment Report. North Coast Watershed Assessment Program. California Resources
Agency, and California Environmental Protection Agency, Sacramento, California. |
- . . C.0.d.1
Project Monitoring (LOV)
- . . C.0.d.2
Monitoring Location (LOV)
- . . C.4
Instream Habitat ProjectY (Y/N)
- . . . . C.4.a
Instream Habitat Funding 284,680.00
- . . . . C.4.b
Total length of instream habitat treated .88
- . . . . C.4.d.1
Channel structure placementY (Y/N)
- . . . . . . C.4.d.2
Material used for channel structure (LOV)
- . . . . . . C.4.d.3
Miles of stream treated through channel structure placement .88
- . . . . . . C.4.d.5
Pools expected to be created through channel structure placement 0
- . . . . . . C.4.d.7
Number of structures placed in channel 28
|
|