Shifting the Baseline for Salmon Escapement Goals: Causes and Solutions

Salmonid Research, Monitoring, and Evaluation (RM&E)

Research
Project IDAK54004
Recovery Domains -
Start Date03/01/2021
End Date02/28/2023
Year2020
StatusCompleted
Last Edited02/27/2024
 
1 - 1

Description    


This project investigated how temporary shifts in the stock-recruitment relationship might affect the estimated escapement goal. In addition, it looked at how management precision (ability to meet the escapement goal irregardless of the magnitude of the return) might affect the persistence of any biases caused by such a temporary shift. The results showed that the initial contrast in spawning stock abundance in the data set was very important in the ability to reliably estimate escapement goals.

Project Benefit    


Inappropriately low salmon escapement goals risk extirpation of substocks and put future subsistence harvests at risk. This project will investigate whether the recent spate of low escapement goal estimates for troubled Alaskan salmon stocks is warranted or not. If sources of bias are found, fixing them will improve the security of future subsistence harvests. If found to be warranted, this will reassure stakeholders and managers and could improve relationships among them.

Accomplishments

Metric Completed Originally
Proposed

Funding Details

SourceFunds
PCSRF$40,971
State$19,333
Report Total:$60,304


Project Map



Worksites

48584176    


  • Worksite Identifier: 48584176
  • Start Date:
  • End Date:
Area Description

No Area Description data was found for this worksite.

Location Information

  • Basin: Northern Southeast Alaska (190103)
  • Subbasin: Lynn Canal (19010301)
  • Watershed: Admiralty Island-Frontal Lynn Canal (1901030107)
  • Subwatershed: Peterson Creek-Frontal Lynn Canal (190103010714)
  • State: Alaska
  • Recovery Domain:
  • Latitude: 58.392479
  • Longitude: -134.7712

ESU

  • Un-Named ESU Chinook

Map

Photos

Metrics

Metrics
  • E.0 Salmonid Research, Monitoring, and Evaluation (RM&E)Y (Y/N)
    •      . . E.0.a RM&E Funding 60,304.00
    •      . . E.0.b
      Complement habitat restoration project
    •      . . E.0.c
      Project identified in a plan or watershed assessment.
    •      . . E.0.d.1 Number of Cooperating Organizations 0
    •      . . E.0.d.2
      Name Of Cooperating Organizations.
      None
    •      . . E.0.e.1 Number of reports prepared 0
    •      . . E.0.e.2
      Name Of Report
      None
    •      . . E.2 ResearchY (Y/N)
      •      . . . . E.2.a Research Funding 60,304.00
      •      . . . . E.2.b.1 Modeling and data analysisY (Y/N)
        •      . . . . . . E.2.b.1.a
          Key issues addressed by modeling and data analysis research