Skokomish Enetai Creek Hatchery - Modernize, Retrofit, and Upgrade Incubation Facility

Salmonid Hatcheries and Harvest Management

Hatchery Production
Project ID19HR E-5
Recovery DomainsPuget Sound
Start Date06/01/2020
End Date08/31/2022
Year2019
StatusCompleted
Last Edited02/27/2024
 
1 - 1

Description    


This project intended to modernize, retrofit, and upgrade the incubation facility to provide sufficient infrastructure, and incubation space, and increase the number of incubators. Due to structural issues and concerns with the existing incubation facility, this project utilized Best Hatchery Management Practices Criteria and Technological Advances by implementing Redd Zone’s modular hatchery design concept.

Project Benefit    


The project improved overall efficiency and ergonomics and maximized benefits from hatchery production (brood stock to adult return). This project addressed several causative problems and factors, including: inadequate incubation conditions, low green egg to eyed survival rates due to high loading densities, and repeated incidence of environmental gill disease, which in some cases has led to bacterial gill disease requiring treatment which indicates that something is fundamentally wrong with the hatchery operation or physical set-up of the hatchery.

Accomplishments

Metric Completed Originally
Proposed

Funding Details

SourceFunds
PCSRF$100,000
Report Total:$100,000


Project Map



Worksites

46813976    


  • Worksite Identifier: 46813976
  • Start Date:
  • End Date:
Area Description

No Area Description data was found for this worksite.

Location Information

  • Basin: Puget Sound (171100)
  • Subbasin: Hood Canal (17110018)
  • Watershed: Lilliwaup Creek-Frontal Hood Canal (1711001803)
  • Subwatershed: Finch Creek-Frontal Hood Canal (171100180301)
  • State: Washington
  • Recovery Domain: Puget Sound
  • Latitude: 47.356461
  • Longitude: -123.160071

ESU

  • Puget Sound/Strait of Georgia Chum Salmon ESU

Map

Photos

Metrics

Metrics
  • D.0 Salmonid Hatcheries and Harvest ManagementY (Y/N)
    •      . . D.0.a Hatchery and harvest mgmt. funding 100,000.00
    •      . . D.0.b
      Complement habitat restoration project
    •      . . D.0.c
      Project Identified in a plan or watershed assessment.
    •      . . D.1 Hatchery Production ProjectY (Y/N)
      •      . . . . D.1.a Hatchery Production Funding 100,000.00
      •      . . . . D.1.c.1 Hatchery operations - facility or equipmentY (Y/N)
        •      . . . . . . D.1.c.2
          Description of the facility modification and/or equipment purchase
          The supports an incubation facility upgrade utilizing technological advances by implementing Redd Zone’s modular hatchery design concept.
        •      . . . . . . D.1.c.3 Funding for facility equipment or structures 100,000.00