Bear Creek Bridge Design

Salmonid Restoration Planning and Assessments

Restoration Planning And Coordination
Project ID003 17 CW
Recovery DomainsSnake River
Start Date12/01/2018
End Date12/31/2020
Year2017
StatusCompleted
Last Edited01/25/2024
 
1 - 1

Description    


The Bear Creek Bridge Design project completed a bridge design to replace an existing bridge over Bear Creek, a tributary to Big Canyon Creek, a tributary to the Clearwater River. Project funds were used to complete the following: 1) hydraulic analysis, 2) channel stability assessment, 3) project survey, 4) environmental compliance documents for the installation phase, 5) engineering design package to use for construction, and 6) a written implementation plan which included pollution control and the dewatering plan for construction phase. A flood occurred in April 2019 which deposited a significant amount of gravel under and upstream of the bridge. Additional survey and design work was completed for a channel modification component of the design.

The project site is located in the Big Canyon Creek Watershed which is a priority watershed for restoration implementation in the Lower Clearwater Steelhead population, Clearwater River MPG, Snake River Steelhead DPS and has been identified as such in the NMFS 2017 ESA steelhead recovery plan. Components of the design were installed in 2019 through PCSRF project #017 18 CW. The bridge, channel rehabilitation, vegetative plantings, and one rock weir were installed per the design and restored access to 2.7 miles of upstream steelhead habitat.

Project Benefit    


Bear Creek is approximately 1.5 miles upstream from the confluence of Big Canyon Creek and the Clearwater River. This creek has perennial flow and is spring fed. Bedload is deposited on the upstream side of an existing bridge creating an annual passage barrier from March through June, which is coincidental to migration and spawning of wild steelhead. This is the only passage barrier identified in Bear Creek and once removed will open approximately 2.1 miles of good upstream spawning habitat.

Accomplishments

Metric Completed Originally
Proposed

Funding Details

SourceFunds
PCSRF$51,523
Other$18,057
In-Kind Volunteers$1,512
Report Total:$71,092


Project Map



Worksites

Bear Creek Bridge    


  • Worksite Identifier: Bear Creek Bridge
  • Start Date: 12/01/2019
  • End Date: 12/31/2020
Area Description
Bear Creek

Location Information

  • Basin: Clearwater (170603)
  • Subbasin: Clearwater (17060306)
  • Watershed: Big Canyon Creek (1706030606)
  • Subwatershed: Nichols Canyon-Big Canyon Creek (170603060607)
  • State: Idaho
  • Recovery Domain: Snake River
  • Latitude: 46.478433
  • Longitude: -116.425155

ESU

  • Snake River Basin Steelhead DPS

Map

Photos

Metrics

Metrics
  • B.0 Salmonid Restoration Planning and AssessmentsY (Y/N)
    •      . . B.0.a Planning And Assessment Funding 71,092.00
    •      . . B.0.b.1 Area Encompassed 1.0
    •      . . B.0.b.2 Stream Miles Affected 2.70
    •      . . B.1 Restoration Planning And CoordinationY (Y/N)
      •      . . . . B.1.a Planning and Coordination funding 71,092.00
      •      . . . . B.1.b.11 Engineering/design work for restoration projectsY (Y/N)
        •      . . . . . . B.1.b.11.a
          Name of plan implemented
          NMFS. 2017. ESA Recovery Plan for Snake River Spring/Summer Chinook Salmon (Oncorhynchus tshawytscha) & Snake River Steelhead (Oncorhynchus mykiss), Portland Oregon.
        •      . . . . . . B.1.b.11.b
          Description and scope of the plan implemented
          The bridge design and construction (under a separate PCSRF contract) implemented priority actions in a priority watershed as directed by Appendix C of the 2017 plan, Chapter 6, pgs. 58-59. Big Canyon Creek is specifically listed as a priority watershed. General habitat restoration priorities for this population that this project addressed (as listed on page 59 of the Recovery Plan) include the following: 1. Restore hydrologic processes to retain surface flow by reducing surface runoff from altered land surfaces, disconnecting artificial drainage systems from natural drainage systems, and modifying water uses. This will contribute to reducing stream temperature problems. This project will restore connectivity by improving the hydrologic function of the stream at the bridge location. 2. Restore channel-forming processes by reestablishing floodplains in incised channels, removing or setting back flood control structures, and rehabilitating stream channels that have been straightened. This project rehabilitated 363 lf of stream channel that was straightened. 3. Reestablish riparian vegetation to create shade for streams. Riparian vegetation will be re-established along 250 lf of channel. 4. Inventory, prioritize, and eliminate remaining artificial fish migration barriers. This site is a seasonal barrier. In addition, the bridge is one component of an overall habitat restoration plan which includes barrier removal and channel condition improvements.