Pahsimeroi River P-17 Diversion: Robins Posada Ranch Easement Acquisition

Salmonid Habitat Restoration and Acquisition

Fish Passage Improvement Fish Screening Instream Flow Land or Easement Acquisition Riparian Habitat
Project ID004 16 SA
Recovery DomainsSnake River
Start Date10/01/2017
End Date06/21/2019
Year2016
StatusTerminated
Last Edited01/25/2024
 
1 - 1

Description    


Worksite #1- Robins Ranch: The Nature Conservancy was awarded funds to purchase a conservation easement over the Robins Ranch in 2017 and worked with a buyer that had the property under contract. They were successful in purchasing the property and determined that they were no longer interested in pursuing a conservation easement at this time. Negotiations broke down when the buyer requested additional building envelopes, a second bridge crossing, and other allowances that were not in-line with the intent of the easement. The landowner ended negotiations.

Worksite #2 - Posada Ranch: The Posada property was not meant to be a standalone project, and once the Robins Ranch component of the project was not viable, a path forward that included acceptable outcomes on the Posada Ranch property was not able to be identified.

Project Benefit    


This project will implement three priority actions identified in the NMFS proposed recovery plan to benefit two populations: Snake River spring/summer Chinook Salmon ESU, upper Salmon MPG, Pahsimeroi River population and the Snake River steelhead DSP, Salmon MPG, Pahsimeroi River population, both of which are ESA-listed as threatened. These actions include the following: 1) Increase stream flows in the mainstem to access historic spawning areas in the upper Pahsimeroi mainstem and its tributaries. 2. Modify passage barriers caused by irrigation diversion structures. 3) Install fish screens.

TNC, in coordination with federal, state, and local partners, will accomplish restoration and protection goals in the following ways:

1. Purchase and secure conservation easements on both Robins and Posada Ranches in order to better coordinate restoration and water conservation activities.
2. Permanently protect all conservation values including spawning habitat for anadromous fish and riparian habitat, and ensure protection of future conservation actions on the properties.
3. Commit landowners to engage in restoration activities to improve habitat in the Pahsimeroi River.
4. Commit landowners to improve water management in order to increase instream flow in the middle Pahsimeroi River.
5. Monitor conservation easement for compliance annually and in perpetuity.

Accomplishments

Metric Completed Originally
Proposed
Land Acquisition
  Acres Acquired or Protected .0 620.0
  Stream Bank Miles Acquired
  or Protected
.00 1.13
Riparian Habitat
  Stream Miles Treated .00 2.26
  Acres Treated .0 27.4
Fish Passage
  Barriers Removed 0 1
  Miles Opened .00 2.76
Fish Screens
  Screens Installed 0 1

Funding Details

SourceFunds
PCSRF$25,994
Other$78,934
Report Total:$104,928


Project Map



Worksites

Robins    


  • Worksite Identifier: Robins
  • Start Date: 06/02/2017
  • End Date: 09/30/2020
Area Description
Pahsimeroi River - middle mainstem

Location Information

  • Basin: Salmon (170602)
  • Subbasin: Pahsimeroi (17060202)
  • Watershed: Lower Pahsimeroi River (1706020203)
  • Subwatershed:
  • State: Idaho
  • Recovery Domain: Snake River
  • Latitude: 44.510017
  • Longitude: -113.839602

ESU

  • Snake River Basin Steelhead DPS
  • Snake River Spring/Summer-run Chinook Salmon ESU

Map

Photos

Metrics

Metrics
  • C.0 Salmonid Habitat Restoration and AcquisitionY (Y/N)
    •      . . C.0.a Habitat restoration and acquisition funding 69,697.00
    •      . . C.0.b Length of stream treated/protected .00
    •      . . C.0.c
      Project identified in a Plan or Watershed Assessment
    •      . . C.0.d.1 Project Monitoring (LOV)
    •      . . C.0.d.2 Monitoring Location (LOV)
    •      . . C.1 Fish Screening ProjectY (Y/N)
      •      . . . . C.1.a Fish screen funding .00
      •      . . . . C.1.c.1 Fish screens installedY (Y/N)
        •      . . . . . . C.1.c.2 Number of new fish screens installed 0
        •      . . . . . . C.1.c.3 Flow rate of screened water 0 (cfs)
      •      . . C.2 Fish Passage ImprovementY (Y/N)
        •      . . . . C.2.a Fish Passage Funding .00
        •      . . . . C.2.b.1 Length of stream made accessible .00
        •      . . . . C.2.b.3 Type of blockage/barrier (LOV)
        •      . . . . C.2.b.4 Number of blockages/impediments/barriers impeding passage 0
        •      . . . . C.2.c.1 Fish passage blockages removed or altered (other than road crossings reported in C.2.f to C.2.i)Y (Y/N)
          •      . . . . . . C.2.c.2 Number of blockages/impediments/barriers removed/altered 0
        •      . . C.3 Instream Flow ProjectY (Y/N)
          •      . . . . C.3.a Instream Flow Funding 30,906.00
          •      . . . . C.3.b Length of stream 'protected' for adequate flow .00
          •      . . . . C.3.c Change in water flow0 (cfs)
          •      . . . . C.3.e.1 Irrigation practice improvementY (Y/N)
            •      . . . . . . C.3.e.2 Acre feet of water conserved per year0 (Acre feet)
            •      . . . . . . C.3.e.3 cfs (cubic feet per second) of water conserved0 (cfs)
            •      . . . . . . C.3.e.4 Initial start date of action or agreement12/31/9999 (mm/dd/yyyy)
            •      . . . . . . C.3.e.5 Final end date of action or agreement12/31/9999 (mm/dd/yyyy)
          •      . . C.5 Riparian Habitat ProjectY (Y/N)
            •      . . . . C.5.a Riparian Habitat Funding 25,049.00
            •      . . . . C.5.b.1 Total riparian miles streambank treated .00
            •      . . . . C.5.b.2 Total Riparian Acres Treated .0
            •      . . . . C.5.d.1 FencingY (Y/N)
              •      . . . . . . C.5.d.2 Miles of fence along stream .00
              •      . . . . . . C.5.d.3 Acres of riparian area protected by fencing .0
            •      . . . . C.5.f.1 Water gap developmentY (Y/N)
              •      . . . . . . C.5.f.2 Number of water gap installations 0
            •      . . C.10 Land or Easement AcquisitionY (Y/N)
              •      . . . . C.10.a Land acquisition funding 13,742.00
              •      . . . . C.10.b Habitat treatments applied (LOV)
              •      . . . . C.10.c.1 Acquisition or lease of land, wetland or estuarine area for conservationY (Y/N)
                •      . . . . . . C.10.c.2 Type of acquisition to protect habitat (LOV)
                •      . . . . . . C.10.c.3 Type of property protected (LOV)
                •      . . . . . . C.10.c.4 Date of expiration of protection12/31/9999 (mm/dd/yyyy)
                •      . . . . . . C.10.c.5 Miles of streambank protected by land or easement acquisition .00
                •      . . . . . . C.10.c.6 Acres of land, wetland or estuarine area acquired .0

Posada    


  • Worksite Identifier: Posada
  • Start Date: 06/02/2017
  • End Date: 12/29/2020
Area Description
Pahsimeroi River - middle mainstem

Location Information

  • Basin: Salmon (170602)
  • Subbasin: Pahsimeroi (17060202)
  • Watershed: Lower Pahsimeroi River (1706020203)
  • Subwatershed:
  • State: Idaho
  • Recovery Domain: Snake River
  • Latitude: 44.522257
  • Longitude: -113.854795

ESU

  • Snake River Basin Steelhead DPS
  • Snake River Spring/Summer-run Chinook Salmon ESU

Map

Photos

Metrics

Metrics
  • C.0 Salmonid Habitat Restoration and AcquisitionY (Y/N)
    •      . . C.0.a Habitat restoration and acquisition funding 35,231.00
    •      . . C.0.b Length of stream treated/protected .00
    •      . . C.0.c
      Project identified in a Plan or Watershed Assessment
    •      . . C.0.d.1 Project Monitoring (LOV)
    •      . . C.0.d.2 Monitoring Location (LOV)
    •      . . C.3 Instream Flow ProjectY (Y/N)
      •      . . . . C.3.a Instream Flow Funding 22,979.00
      •      . . . . C.3.b Length of stream 'protected' for adequate flow .00
      •      . . . . C.3.c Change in water flow0 (cfs)
      •      . . . . C.3.e.1 Irrigation practice improvementY (Y/N)
        •      . . . . . . C.3.e.2 Acre feet of water conserved per year0 (Acre feet)
        •      . . . . . . C.3.e.3 cfs (cubic feet per second) of water conserved0 (cfs)
        •      . . . . . . C.3.e.4 Initial start date of action or agreement12/31/9999 (mm/dd/yyyy)
        •      . . . . . . C.3.e.5 Final end date of action or agreement12/31/9999 (mm/dd/yyyy)
      •      . . C.10 Land or Easement AcquisitionY (Y/N)
        •      . . . . C.10.a Land acquisition funding 12,252.00
        •      . . . . C.10.b Habitat treatments applied (LOV)
        •      . . . . C.10.c.1 Acquisition or lease of land, wetland or estuarine area for conservationY (Y/N)
          •      . . . . . . C.10.c.2 Type of acquisition to protect habitat (LOV)
          •      . . . . . . C.10.c.3 Type of property protected (LOV)
          •      . . . . . . C.10.c.4 Date of expiration of protection12/31/9999 (mm/dd/yyyy)
          •      . . . . . . C.10.c.5 Miles of streambank protected by land or easement acquisition .00
          •      . . . . . . C.10.c.6 Acres of land, wetland or estuarine area acquired .0