Mission Creek Fish Passage Project - Tallant Road Bridge
Salmonid Habitat Restoration and Acquisition
|
723327 | S. California - S. Central CA Coast | 06/07/2010 | 05/01/2012 | 2009 | Completed | 05/08/2024 | |
| |
Description
Modify concrete grade control structure at the Tallant Road bridge to improve fish passage.
Project Benefit
The primary goal of the project is to improve upstream migration of the endangered steelhead trout in order to provide access to their historic spawning grounds and eventually restore a healthy population of steelhead in Mission Creek.
Accomplishments
Instream Habitat |
Stream Miles Treated |
.06 |
.06 |
Fish Passage |
Barriers Removed |
|
|
Miles Opened |
2.00 |
2.00 |
Funding Details |
State | $395,678 |
Other | $184,755 |
Report Total: | $580,433 |
|
| |
Worksites
7209117
- Worksite Identifier: 7209117
- Start Date:
- End Date:
Area Description
Tallant Road Bridge
Location Information
- Basin: Central California Coastal (180600)
- Subbasin:
- Watershed:
- Subwatershed:
- State: California
- Recovery Domain: S. California - S. Central CA Coast
- Latitude: 34.43215
- Longitude: -119.726982
ESU
- Southern California Steelhead DPS
Map
Photos
Metrics
Metrics
- C.0
Salmonid Habitat Restoration and AcquisitionY (Y/N)
- . . C.0.a
Habitat restoration and acquisition funding 580,433.00
- . . C.0.b
Length of stream treated/protected .06
- . . C.0.c
Project identified in a Plan or Watershed Assessment | |
Steelhead Assessment and Recovery Opportunities in Southern Santa Barbara County, CA. Stoecker and Conception Coast 2002 |
- . . C.0.d.1
Project Monitoring (LOV)
- . . C.0.d.2
Monitoring Location (LOV)
- . . C.2
Fish Passage ImprovementY (Y/N)
- . . . . C.2.a
Fish Passage Funding 290,216.00
- . . . . C.2.b.1
Length of stream made accessible 2.00
- . . . . C.2.b.3
Type of blockage/barrier (LOV)
- . . . . C.2.b.4
Number of blockages/impediments/barriers impeding passage 2
- . . . . C.2.g.1
Bridge installed or improved at road stream crossingY (Y/N)
- . . . . . . C.2.g.2
Number of bridges installed or improved/upgraded 2
- . . . . . . C.2.g.3
Miles of stream made accessible by bridge installation or improvement/upgrade 2.00
- . . C.4
Instream Habitat ProjectY (Y/N)
- . . . . C.4.a
Instream Habitat Funding 290,217.00
- . . . . C.4.b
Total length of instream habitat treated .06
- . . . . C.4.c.1
Channel reconfiguration and connectivityY (Y/N)
- . . . . . . C.4.c.2
Type of change to channel configuration and connectivity (LOV)
- . . . . . . C.4.c.3
Miles of stream treated for channel reconfiguration and connectivity .06
- . . . . . . C.4.c.4
Miles of off-channel stream created through channel reconfiguration and connectivity .00
- . . . . . . C.4.c.6
Instream pools created/added through channel reconfiguration and connectivity 3
|
|