Mission Creek Fish Passage Project at Tallant Road Bridge

Salmonid Restoration Planning and Assessments

Restoration Planning And Coordination
Project ID722796
Recovery DomainsS. California - S. Central CA Coast
Start Date05/01/2008
End Date04/29/2010
Year2007
StatusCompleted
Last Edited05/08/2024
 
1 - 1

Description    


Completed construction-level design and specifications for fish passage improvement project at Tallant Road Bridge, including obtaining necessary permits and CEQA review.

Project Benefit    


The primary goal of the project is to improve upstream migration of steelhead trout at the third impassable barrier in order to provide access to their historic spawning grounds and ultimately restore a healthy population of steelhead in Mission Creek. In addition, the project aims to improve riparian and streamside habitat for other species by creating a stable channel bed and banks, and improving the riparian canopy and native plant cover. Without removal of this key barrier, steelhead will not be able to reach spawning and rearing habitat within Mission Creek, which if not corrected soon, could ultimately lead to extirpation of this species from Mission Creek.

Accomplishments

Metric Completed Originally
Proposed

Funding Details

SourceFunds
PCSRF$48,944
Report Total:$48,944


Project Map



Worksites

7208131    


  • Worksite Identifier: 7208131
  • Start Date:
  • End Date:
Area Description
Mission Creek - Tallant Road Bridge (fish passage planning)

Location Information

  • Basin: Central California Coastal (180600)
  • Subbasin:
  • Watershed:
  • Subwatershed:
  • State: California
  • Recovery Domain: S. California - S. Central CA Coast
  • Latitude: 34.432135
  • Longitude: -119.726954

ESU

  • Southern California Steelhead DPS

Map

Photos

Metrics

Metrics
  • B.0 Salmonid Restoration Planning and AssessmentsY (Y/N)
    •      . . B.0.a Planning And Assessment Funding 48,944.00
    •      . . B.0.b.1 Area Encompassed .0
    •      . . B.1 Restoration Planning And CoordinationY (Y/N)
      •      . . . . B.1.a Planning and Coordination funding 48,943.75
      •      . . . . B.1.b.11 Engineering/design work for restoration projectsY (Y/N)
        •      . . . . . . B.1.b.11.a
          Name of plan implemented
          Mission Creek Fish Passage Project at Tallant Road Bridge
        •      . . . . . . B.1.b.11.b
          Description and scope of the plan implemented
          Address the need to remove the apron downstream of the Tallant Road Bridge and reconstruct the channel bed downstream to create a stable and passable transition to the channel above Tallant Road Bridge.