Pudding Creek Watershed Restoration Project
Salmonid Habitat Restoration and Acquisition
|
704835 | N Central California Coast | 05/01/2003 | 04/19/2006 | 2002 | Completed | 01/26/2024 | |
| |
Description
Remediate approximately 14,006 cu yds of potential sediment delivery to salmonid streams, including sediment control upgrades at 46 sites along 6.2 miles of road on Cambell Timerland, Inc.
Project Benefit
Improve: Excessive sediment
Funding Details |
PCSRF | $78,121 |
Report Total: | $78,121 |
|
| |
Worksites
7004951
- Worksite Identifier: 7004951
- Start Date:
- End Date:
Area Description
Pudding Creek Watershed - Pudding Creek Road 15000 (road upgrade)
Location Information
- Basin: Northern California Coastal (180101)
- Subbasin:
- Watershed: Pudding Creek-Frontal Pacific Ocean
- Subwatershed:
- State: California
- Recovery Domain: N Central California Coast
- Latitude: 39.474258
- Longitude: -123.704051
ESU
- Central California Coast Coho Salmon ESU
Map
Photos
Metrics
Metrics
- C.0
Salmonid Habitat Restoration and AcquisitionY (Y/N)
- . . C.0.a
Habitat restoration and acquisition funding 39,060.00
- . . C.0.b
Length of stream treated/protected 3.10
- . . C.0.c
Project identified in a Plan or Watershed Assessment | |
N/A |
- . . C.0.d.1
Project Monitoring (LOV)
- . . C.0.d.2
Monitoring Location (LOV)
- . . C.6
Upland Habitat And Sediment ProjectY (Y/N)
- . . . . C.6.a
Upland Habitat / Sediment Funding 39,060.48
- . . . . C.6.b.1
Acres of upland habitat area treated .0
- . . . . C.6.b.2
Miles of road treated in upland area 5.10
- . . . . C.6.c.1
Road drainage system improvements and reconstructionY (Y/N)
- . . . . . . C.6.c.2
Miles of road treated for drainage system improvements and reconstruction 5.10
7004952
- Worksite Identifier: 7004952
- Start Date:
- End Date:
Area Description
Pudding Creek Watershed - Pudding Creek Road 15700 (road upgrade)
Location Information
- Basin: Northern California Coastal (180101)
- Subbasin:
- Watershed: Pudding Creek-Frontal Pacific Ocean
- Subwatershed:
- State: California
- Recovery Domain: N Central California Coast
- Latitude: 39.467898
- Longitude: -123.669349
ESU
- Central California Coast Coho Salmon ESU
Map
Photos
Metrics
Metrics
- C.0
Salmonid Habitat Restoration and AcquisitionY (Y/N)
- . . C.0.a
Habitat restoration and acquisition funding 39,060.00
- . . C.0.b
Length of stream treated/protected 3.10
- . . C.0.c
Project identified in a Plan or Watershed Assessment | |
N/A |
- . . C.0.d.1
Project Monitoring (LOV)
- . . C.0.d.2
Monitoring Location (LOV)
- . . C.6
Upland Habitat And Sediment ProjectY (Y/N)
- . . . . C.6.a
Upland Habitat / Sediment Funding 39,060.48
- . . . . C.6.b.1
Acres of upland habitat area treated .0
- . . . . C.6.b.2
Miles of road treated in upland area .77
- . . . . C.6.c.1
Road drainage system improvements and reconstructionY (Y/N)
- . . . . . . C.6.c.2
Miles of road treated for drainage system improvements and reconstruction .77
|
|