SBT-Habitat-Herd Creek-Fish Screen
Salmonid Restoration Planning and Assessments
|
SBT-Habitat-07 | Snake River | 10/01/2002 | 12/31/2005 | 2002 | Completed | 05/08/2024 | |
| |
Description
Fish passage blockage looked at by landowner, Tribes, and agencies. Completed engineering design with Bureau of Reclamation and initiated a Memorandum of Agreement between the Bureau of Reclamation and Tribes.
Funding Details |
PCSRF | $5,347 |
Report Total: | $5,347 |
|
| |
Worksites
1779
- Worksite Identifier: 1779
- Start Date:
- End Date:
Area Description
No Area Description data was found for this worksite.
Location Information
- Basin: Salmon (170602)
- Subbasin: Upper Salmon
- Watershed:
- Subwatershed:
- State: Idaho
- Recovery Domain: Snake River
- Latitude: 44.0999997045379
- Longitude: -114.25555616746
ESU
- Snake River Basin Steelhead DPS
- Snake River Spring/Summer-run Chinook Salmon ESU
Map
Photos
Metrics
Metrics
- B.0
Salmonid Restoration Planning and AssessmentsY (Y/N)
- . . B.0.a
Planning And Assessment Funding 5,347.00
- . . B.1
Restoration Planning And CoordinationY (Y/N)
- . . . . B.1.a
Planning and Coordination funding 5,347.00
- . . . . B.1.b.11
Engineering/design work for restoration projectsY (Y/N)
|
|