ODFW LCR Chum Reintroduction - Coordination 2022
Salmonid Restoration Planning and Assessments
|
OWEB 222-905-22796 | Lower Columbia River | 07/01/2022 | 06/30/2024 | 2022 | Completed | 05/03/2025 | |
| |
Description
The purpose of this project was to coordinate activities within ODFW and among other agencies to reintroduce Chum Salmon to the Lower Columbia River. Activities included: coordinating broodstock collection at Big Creek Hatchery, chairing the Lower Columbia River Chum Salmon Workgroup, developing outplanting strategies and sampling designs, supporting habitat restoration projects, and coordinating with the Washington Department of Fish and Wildlife to implement reintroduction goals.
Project Benefit
This project will work to implement the Lower Columbia River Conservation and Recovery Plan for Oregon Populations of Salmon and Steelhead. This will include tactical projects such as maintenance of a conservation broodstock as well as coordination with other agencies to identify and efficiently implement reintroduction strategies. Specifically, a coordinated reintroduction effort with the Washington Department of Fish and Wildlife will provide a strong foundation for future research and restoration of Chum Salmon in the Lower Columbia. Identifying priorities for restoration will help attract restoration funding and ensure it is used where it is most effective.
Funding Details |
PCSRF | $120,383 |
Report Total: | $120,383 |
|
| |
Worksites
60935949
- Worksite Identifier: 60935949
- Start Date:
- End Date:
Area Description
No Area Description data was found for this worksite.
Location Information
- Basin: Lower Columbia (170800)
- Subbasin:
- Watershed:
- Subwatershed:
- State: Oregon
- Recovery Domain: Lower Columbia River
- Latitude: 45.45312
- Longitude: -122.07771
ESU
- Columbia River Chum Salmon ESU
Map
Photos
Metrics
Metrics
- B.0
Salmonid Restoration Planning and AssessmentsY (Y/N)
- . . B.0.a
Planning And Assessment Funding 120,382.55
- . . B.0.b.1
Area Encompassed 313,905.8
- . . B.1
Restoration Planning And CoordinationY (Y/N)
- . . . . B.1.a
Planning and Coordination funding 120,382.55
- . . . . B.1.b.2
Coordination on implementation of a Recovery PlanY (Y/N)
- . . . . . . B.1.b.2.a
Name of the Recovery Plan Implemented | |
Lower Columbia River Conservation and Recovery Plan for Oregon Populations of Salmon and Steelhead (ODFW, 2010), , |
- . . . . . . B.1.b.2.b
Description and scope of the Recovery Plan implemented | |
The plan implements work for four Lower Columbia River/Columbia River ESUs/DPS: coho, Chinook, steelhead, and chum. Several key components of the plan will be implemented, including Oregon's Columbia River Chum Salmon Recovery Strategy. |
- . . . . B.1.b.3
Coordination of watershed conservation and restoration effortsY (Y/N)
- . . . . . . B.1.b.3.a
Name of plan | |
Lower Columbia River Conservation and Recovery Plan for Oregon Populations of Salmon and Steelhead (ODFW, 2010)
, , |
- . . . . . . B.1.b.3.b
Description and scope of the plan implemented | |
The plan implements work for four Lower Columbia River/Columbia River ESUs/DPS: coho, Chinook, steelhead, and chum. Several key components of the plan will be implemented, including Oregon's Columbia River Chum Salmon Recovery Strategy. |
- . . . . B.1.b.8
Conducting habitat restoration scoping and feasibility studiesY (Y/N)
- . . . . . . B.1.b.8.a
Name of plan implemented | |
Lower Columbia River Conservation and Recovery Plan for Oregon Populations of Salmon and Steelhead (ODFW, 2010)
, , |
- . . . . . . B.1.b.8.b
Description and scope of the plan implemented | |
The plan implements work for four Lower Columbia River/Columbia River ESUs/DPS: coho, Chinook, steelhead, and chum. Several key components of the plan will be implemented, including Oregon's Columbia River Chum Salmon Recovery Strategy. |
|
|