Walla Walla B2B Phase 3 Design
Salmonid Restoration Planning and Assessments
|
19-1497 P | Middle Columbia River | 12/12/2019 | 12/31/2023 | 2019 | Completed | 05/01/2025 | |
| |
Description
This project completed final designs on the Phase 3 segment of the Bridge to Bridge project reach on the Walla Walla River near Lowden, WA. The contracted engineering firm GeoEngineers provided updated design and bid documents including new plan set, quantities, and cost estimates. This section of the Walla Walla River is identified by the Snake River Recovery Board as a priority restoration reach and major spawning area. Adult and juvenile summer steelhead and spring Chinook occupy this project reach during migration, and bull trout occur here seasonally. Other species of cultural value and state concern (lamprey, margined sculpin, and leopard dace) inhabit this location.
The project area was originally designed under SRFB 14-1902. This project creates a design in response to a major avulsion on the Walla Walla river that cause the original project design to not provide the salmon benefit of the original porject goals and objectives. This project footprint covers 45 acres and .52 river miles of previously reported project areas.
Project Benefit
Improve instream habitat and increase the quality and accessibility of off-channel and high flow refuge habitat in the project reach for steelhead, spring Chinook, Bull Trout, Margined Sculpin, Leopard Dace, and River Lamprey.
Funding Details |
State | $54,427 |
Other | $9,605 |
Report Total: | $64,031 |
|
| |
Worksites
1-Walla Walla B2B Phase 3 Des
- Worksite Identifier: 1-Walla Walla B2B Phase 3 Des
- Start Date:
- End Date:
Area Description
No Area Description data was found for this worksite.
Location Information
- Basin: Middle Columbia (170701)
- Subbasin:
- Watershed:
- Subwatershed:
- State: Washington
- Recovery Domain: Middle Columbia River
- Latitude: 46.04403789
- Longitude: -118.52943393
ESU
- Middle Columbia River Steelhead DPS
- Un-Named ESU Chinook
Map
Photos
Metrics
Metrics
- B.0
Salmonid Restoration Planning and AssessmentsY (Y/N)
- . . B.0.a
Planning And Assessment Funding 64,031.00
- . . B.0.b.1
Area Encompassed .0
- . . B.0.b.2
Stream Miles Affected .00
- . . B.1
Restoration Planning And CoordinationY (Y/N)
- . . . . B.1.a
Planning and Coordination funding 64,031.00
- . . . . B.1.b.11
Engineering/design work for restoration projectsY (Y/N)
- . . . . . . B.1.b.11.a
Name of plan implemented | |
Snake River Salmon Recovery Board (2011 Version) Snake River
Salmon Recovery Plan for SE Washington. Dayton, WA. Snake
River Salmon Recovery Board (2019 Version) Snake River Salmon
Recovery Region Provisional 3-5 Year Work Plan. Dayton, WA. |
- . . . . . . B.1.b.11.b
Description and scope of the plan implemented | |
Priority Restoration Reach (Funding Habitat Restoration Projects for Salmon Recovery in the Snake River Region; page 18) Major Spawning Area (Snake River Salmon Recovery Plan; page 98,
104) |
|
|