Tarboo Creek Habitat Restoration Project
Salmonid Habitat Restoration and Acquisition
|
01-1312 R | Puget Sound | 10/01/2002 | 08/31/2004 | 2001 | Completed | 05/01/2025 | |
| |
Description
The Hood Canal Salmon Enhancement Group used this funding for a cooperative fish passage project with Jefferson County, the Point no Point Treaty Tribes, the US Fish & Wildlife Service, and the National Fish and Wildlife Foundation. We replaced two undersized culverts on Tarboo Creek that were perched and too small. Both of these culverts were determined to be total blockages to salmonids as determined by the Washington State Department of Fish and Wildlife. The one under Dabob Road was replaced with a 12’ structural plate aluminum culvert and the one under Center Road was replaced with a 15 pipe arch aluminum culvert. This project opened 3.8 miles of the north and south stems of Tarboo Creek, which opened 1,691 acres of the 7,000 acre Tarboo watershed that is habitat to chum, coho, cutthroat trout, and steelhead.
Project Benefit
The goal of the project is to connect isolated habitat to increase the range and distribution of salmon.
The objective of the project is to increase access to areas blocked by human-caused impediments.
Accomplishments
Fish Passage |
Barriers Removed |
2 |
2 |
Miles Opened |
3.80 |
5.20 |
Funding Details |
State | $251,510 |
Other | $311,419 |
Report Total: | $562,929 |
|
| |
Worksites
2-Tarboo Cr. Culvert Replacem
- Worksite Identifier: 2-Tarboo Cr. Culvert Replacem
- Start Date:
- End Date:
Area Description
No Area Description data was found for this worksite.
Location Information
- Basin: Puget Sound (171100)
- Subbasin:
- Watershed:
- Subwatershed:
- State: Washington
- Recovery Domain: Puget Sound
- Latitude: 47.91609844
- Longitude: -122.82434621
ESU
No ESU data was found for this worksite.
Map
Photos
Metrics
Metrics
- C.0
Salmonid Habitat Restoration and AcquisitionY (Y/N)
- . . C.0.a
Habitat restoration and acquisition funding 260,000.00
- . . C.0.b
Length of stream treated/protected .25
- . . C.0.c
Project identified in a Plan or Watershed Assessment | |
na |
- . . C.0.d.1
Project Monitoring (LOV)
- . . C.0.d.2
Monitoring Location (LOV)
- . . C.2
Fish Passage ImprovementY (Y/N)
- . . . . C.2.a
Fish Passage Funding 260,000.00
- . . . . C.2.b.1
Length of stream made accessible 1.90
- . . . . C.2.b.3
Type of blockage/barrier (LOV)
- . . . . C.2.b.4
Number of blockages/impediments/barriers impeding passage 1
- . . . . C.2.c.1
Fish passage blockages removed or altered (other than road crossings reported in C.2.f to C.2.i)Y (Y/N)
- . . . . . . C.2.c.2
Number of blockages/impediments/barriers removed/altered 1
- . . . . C.2.f.1
Culvert installed or improved at road stream crossingY (Y/N)
- . . . . . . C.2.f.2
Number of culverts installed or improved 1
- . . . . . . C.2.f.3
Miles of stream made accessible by culvert installation/upgrade 1.90
1-Tarboo Cr Culvert Repacemen
- Worksite Identifier: 1-Tarboo Cr Culvert Repacemen
- Start Date:
- End Date:
Area Description
No Area Description data was found for this worksite.
Location Information
- Basin: Puget Sound (171100)
- Subbasin:
- Watershed:
- Subwatershed:
- State: Washington
- Recovery Domain: Puget Sound
- Latitude: 47.918838
- Longitude: -122.82237852
ESU
- Puget Sound/Strait of Georgia Coho Salmon ESU
- Hood Canal Summer-run Chum Salmon ESU
- Puget Sound Steelhead DPS
Map
Photos
Metrics
Metrics
- C.0
Salmonid Habitat Restoration and AcquisitionY (Y/N)
- . . C.0.a
Habitat restoration and acquisition funding 302,928.97
- . . C.0.b
Length of stream treated/protected .25
- . . C.0.c
Project identified in a Plan or Watershed Assessment | |
na |
- . . C.0.d.1
Project Monitoring (LOV)
- . . C.0.d.2
Monitoring Location (LOV)
- . . C.2
Fish Passage ImprovementY (Y/N)
- . . . . C.2.a
Fish Passage Funding 302,928.97
- . . . . C.2.b.1
Length of stream made accessible 1.90
- . . . . C.2.b.3
Type of blockage/barrier (LOV)
- . . . . C.2.b.4
Number of blockages/impediments/barriers impeding passage 1
- . . . . C.2.c.1
Fish passage blockages removed or altered (other than road crossings reported in C.2.f to C.2.i)Y (Y/N)
- . . . . . . C.2.c.2
Number of blockages/impediments/barriers removed/altered 1
- . . . . C.2.f.1
Culvert installed or improved at road stream crossingY (Y/N)
- . . . . . . C.2.f.2
Number of culverts installed or improved 1
- . . . . . . C.2.f.3
Miles of stream made accessible by culvert installation/upgrade 1.90
|
|