Lower Manastash Assessment & Project Development
Salmonid Restoration Planning and Assessments
|
10-1838 P | Middle Columbia River | 12/10/2010 | 04/30/2013 | 2010 | Completed | 05/01/2025 | |
| |
Description
The Manastash Creek Reach Assessment identified, quantified, and prioritized salmonid habitat restoration projects in the lower 13 miles of the Manastash Creek watershed. This assessment was planned as major irrigation diversion improvements (screening and passage) and instream flow improvements have been or are in the process of being implemented in the lower 6 miles. With fish passage into the watershed nearly restored, the next logical step is instream and riparian habitat improvements. Major flood events in 2011 peaked interest levels of local landowners and agencies, thus the opportunity was presented to inventory and assess restoration projects that address habitat complexity, floodplain connectivity, riparian habitat, water quantity and water quality. This assessment will be used to guide future project development. It was completed in cooperation with the US Bureau of Reclamation so that it is compatible with the Yakima River Basin Water Enhancement Project (YRBWEP) tributary plan, opening up additional funding avenues for future projects. This project will benefit spring-run Chinook salmon and steelhead.
Project deliverables included 1) 4 meetings of the technical committee to scope and review the reach assessment, 2) 4 public meetings (landowner commitee) to share project information and solicit input, and 3) a reach assessment report that includes a reach by reach analysis of in-channel and riparian habitat conditions and fish passage barriers, prioritization of project opportunities, and 5 conceptual project designs.
Project Benefit
The goal of this assessment project was to assess fish habitat and prioritize fish habitat improvement projects in the lower 13 miles of Manastash Creek. This goal was a scope change from the original goal of removing a fish passage barrier. See narrative for explanation.
Funding Details |
PCSRF | $112,959 |
Other | $44,700 |
Report Total: | $157,659 |
|
| |
Worksites
1-Lower Manastash
- Worksite Identifier: 1-Lower Manastash
- Start Date:
- End Date:
Area Description
No Area Description data was found for this worksite.
Location Information
- Basin: Yakima (170300)
- Subbasin:
- Watershed:
- Subwatershed:
- State: Washington
- Recovery Domain: Middle Columbia River
- Latitude: 46.98517469
- Longitude: -120.6171691
ESU
- Mid-Columbia River Spring-run Chinook Salmon ESU
- Middle Columbia River Steelhead DPS
Map
Photos
Metrics
Metrics
- B.0
Salmonid Restoration Planning and AssessmentsY (Y/N)
- . . B.0.a
Planning And Assessment Funding 157,659.00
- . . B.0.b.1
Area Encompassed 126.0
- . . B.0.b.2
Stream Miles Affected 13.00
- . . B.1
Restoration Planning And CoordinationY (Y/N)
- . . . . B.1.a
Planning and Coordination funding 5,205.00
- . . . . B.1.b.8
Conducting habitat restoration scoping and feasibility studiesY (Y/N)
- . . . . . . B.1.b.8.a
Name of plan implemented | |
Herrera, et al., June 2013, Manastash Creek Corridor Habitat Enhancement and Flood Hazard Reduction Plan. |
- . . . . . . B.1.b.8.b
Description and scope of the plan implemented | |
Reach Assessment Report including: 1) Reach by reach analysis of channel morphology; habitat unit composition; large wood, substrate and fine sediment; instability and disturbance; fish passage barriers; and riparian corridor, 2) Prioritization of project opportunities, and 3) 5 conceptual designs. |
- . . B.2
Salmonid Habitat Assessment / InventoryY (Y/N)
- . . . . B.2.a
Habitat Assessment Funding 152,454.00
- . . . . B.2.d
Habitat surveysY (Y/N)
- . . . . . . B.2.d.1
Type of habitat survey/assessment (LOV)
- . . . . . . B.2.d.2
Amount of habitat assessed 126.0
- . . . . . . B.2.d.3
Amount of habitat assessed that needed restoration 63.0
|
|