Buckeye Creek Instream Habitat Enhancement

Salmonid Habitat Restoration and Acquisition

Instream Habitat
Project ID1611968188128
Recovery DomainsN Central California Coast
Start Date04/27/2021
End Date06/08/2023
Year2018
StatusCompleted
Last Edited05/01/2025
 
1 - 1

Description    


The Project installed 94 key pieces of large woody debris were placed in the active channel at 37 unique structures throughout the total 1.23 mile project reach.

Project Benefit    


This project will increase stream habitat complexity, pool frequency, pool depth, high-flow refugia, and over-summer rearing habitat for steelhead trout and Coho salmon.

Accomplishments

Metric Completed Originally
Proposed
Instream Habitat
  Stream Miles Treated 1.23 1.23

Funding Details

SourceFunds
PCSRF$21,564
In-Kind Other$143,724
Report Total:$165,288


Project Map



Worksites

1611968188353    


  • Worksite Identifier: 1611968188353
  • Start Date:
  • End Date:
Area Description
Worksite 1

Location Information

  • Basin: Northern California Coastal (180101)
  • Subbasin:
  • Watershed:
  • Subwatershed:
  • State: California
  • Recovery Domain: N Central California Coast
  • Latitude: 38.75772
  • Longitude: -123.29862

ESU

  • Northern California Steelhead DPS

Map

Photos

Metrics

Metrics
  • C.0 Salmonid Habitat Restoration and AcquisitionY (Y/N)
    •      . . C.0.a Habitat restoration and acquisition funding 165,288.00
    •      . . C.0.b Length of stream treated/protected 1.23
    •      . . C.0.c
      Project identified in a Plan or Watershed Assessment
    •      . . C.0.d.1 Project Monitoring (LOV)
    •      . . C.0.d.2 Monitoring Location (LOV)
    •      . . C.4 Instream Habitat ProjectY (Y/N)
      •      . . . . C.4.a Instream Habitat Funding 165,288.00
      •      . . . . C.4.b Total length of instream habitat treated 1.23
      •      . . . . C.4.d.1 Channel structure placementY (Y/N)
        •      . . . . . . C.4.d.2 Material used for channel structure (LOV)
        •      . . . . . . C.4.d.3 Miles of stream treated through channel structure placement 1.23
        •      . . . . . . C.4.d.5 Pools expected to be created through channel structure placement 20
        •      . . . . . . C.4.d.6 Yards of average stream-width at mid-point of channel structure placement project10 (Yards)
        •      . . . . . . C.4.d.7 Number of structures placed in channel 94