Kabusie Bridge Restoration Project

Salmonid Habitat Restoration and Acquisition

Fish Passage Improvement
Project ID12-MAKA-04
Recovery Domains -
Start Date08/01/2015
End Date12/31/2015
Year2012
StatusCompleted
Last Edited05/01/2025
 
1 - 1

Description    


Project funds were used to supplement budget costs for construction for an arched concrete bridge at the Kabusie Creek crossing on the BIA Public Road Makah Passage, located on the Makah Reservation. This project was a major milestone in our Tsoo-Yess Basin Anadromous Passage project to re-establish stream habitat floodplain connectivity between the Tsoo-Yess River and its associated floodplain. A concrete bridge replaced the impassable non-functioning culvert. This project was designed to directly benefit fish production by restoring fish passage to one mile of habitat. Planning and preparation for the project started many years ago, however installation was completed during the summer of 2015.

Project Benefit    


Tsoo-Yess River limiting factors addressed are loss of tributary spawning habitat due to fish blocking structures and loss of tributary contributions to summer base flows in the Tsoo-Yess River.

Accomplishments

Metric Completed Originally
Proposed
Fish Passage
  Barriers Removed
  Miles Opened 1.00 1.00

Funding Details

SourceFunds
PCSRF$44,097
Other$128,975
Report Total:$173,072


Project Map



Worksites

Kabusie Bridge Site    


  • Worksite Identifier: Kabusie Bridge Site
  • Start Date:
  • End Date:
Area Description

No Area Description data was found for this worksite.

Location Information

  • Basin: Washington Coastal (171001)
  • Subbasin: Hoh-Quillayute (17100101)
  • Watershed:
  • Subwatershed:
  • State: Washington
  • Recovery Domain:
  • Latitude: 48.28263385725266
  • Longitude: -124.63318567167552

ESU

  • Olympic Peninsula Coho Salmon ESU
  • Olympic Peninsula Steelhead DPS

Map

Photos

Metrics

Metrics
  • C.0 Salmonid Habitat Restoration and AcquisitionY (Y/N)
    •      . . C.0.a Habitat restoration and acquisition funding 173,072.00
    •      . . C.0.b Length of stream treated/protected .01
    •      . . C.0.c
      Project identified in a Plan or Watershed Assessment
      None
    •      . . C.0.d.1 Project Monitoring (LOV)
    •      . . C.0.d.2 Monitoring Location (LOV)
    •      . . C.2 Fish Passage ImprovementY (Y/N)
      •      . . . . C.2.a Fish Passage Funding 173,072.00
      •      . . . . C.2.b.1 Length of stream made accessible 1.00
      •      . . . . C.2.b.3 Type of blockage/barrier (LOV)
      •      . . . . C.2.b.4 Number of blockages/impediments/barriers impeding passage 1
      •      . . . . C.2.g.1 Bridge installed or improved at road stream crossingY (Y/N)
        •      . . . . . . C.2.g.2 Number of bridges installed or improved/upgraded 1
        •      . . . . . . C.2.g.3 Miles of stream made accessible by bridge installation or improvement/upgrade 1.00