Kasilof River SRS Riverbank Restoration
Salmonid Habitat Restoration and Acquisition
|
AK44156 | - | 03/01/2015 | 09/30/2016 | 2014 | Completed | 05/01/2025 | |
| |
Description
In 2016, this project restored 30.5 meters of riverbank to a natural riparian state by installing root wads and brush layering (using willow stems) for bank stabilization and vegetative matting to improve the riparian area. A light penetrating walkway with river access stairs were installed (not originally proposed) as well as an articulated concrete matting walkway, both of which were placed along existing corridors to help localize foot traffic and ultimately protect the existing and restored riverbank.
Project Benefit
This project will restore and protect 30.5 meters of riparian habitat at the Kasilof River State Recreation Site. A healthy riparian system plays an important role in maintaining healthy salmon populations, providing food, shelter, regulated water temperatures, low flow velocity waters, and resting areas that are beneficial to juvenile salmon.
Accomplishments
Instream Habitat |
Stream Miles Treated |
.02 |
.02 |
Riparian Habitat |
Stream Miles Treated |
.02 |
.02 |
Acres Treated |
.1 |
.1 |
Funding Details |
PCSRF | $144,490 |
State | $69,984 |
Report Total: | $214,474 |
|
| |
Worksites
Kasilof River State Recreation Site
- Worksite Identifier: Kasilof River State Recreation Site
- Start Date:
- End Date:
Area Description
No Area Description data was found for this worksite.
Location Information
- Basin: Kenai Peninsula (190203)
- Subbasin: Lower Kenai Peninsula (19020301)
- Watershed:
- Subwatershed:
- State: Alaska
- Recovery Domain:
- Latitude: 60.316867
- Longitude: -151.258617
ESU
- Un-Named ESU Sockeye
- Un-Named ESU Chinook
- Un-Named ESU Coho
- Un-Named ESU Pink
- Un-Named ESU Steelhead
Map
Photos
Metrics
Metrics
- C.0
Salmonid Habitat Restoration and AcquisitionY (Y/N)
- . . C.0.a
Habitat restoration and acquisition funding 214,474.00
- . . C.0.b
Length of stream treated/protected .02
- . . C.0.c
Project identified in a Plan or Watershed Assessment | |
Kenai Peninsula Fish Habitat Partnership |
- . . C.0.d.1
Project Monitoring (LOV)
- . . C.0.d.2
Monitoring Location (LOV)
- . . C.4
Instream Habitat ProjectY (Y/N)
- . . . . C.4.a
Instream Habitat Funding 114,474.00
- . . . . C.4.b
Total length of instream habitat treated .02
- . . . . C.4.e.1
Streambank stabilization Y (Y/N)
- . . . . . . C.4.e.2
Material Used For Streambank Stabilization (LOV)
- . . . . . . C.4.e.3
Miles of streambank stabilized .02
- . . C.5
Riparian Habitat ProjectY (Y/N)
- . . . . C.5.a
Riparian Habitat Funding 100,000.00
- . . . . C.5.b.1
Total riparian miles streambank treated .02
- . . . . C.5.b.2
Total Riparian Acres Treated .1
- . . . . C.5.c.1
Riparian plantingY (Y/N)
- . . . . . . C.5.c.2
Species of plants planted in riparian | |
Native vegetative matting |
- . . . . . . C.5.c.3
Acres planted in riparian .1
- . . . . C.5.e.1
Riparian exclusionY (Y/N)
- . . . . . . C.5.e.3
Miles of riparian streambank protected by exclusion other than fencing .02
|
|