Project 2001-021-00:15 Mile Creek Riparian Buffers, Contract 88260:2001-021-00 EXP WASCO COUNTY RIPARIAN BUFFERS

Instream Flow; Land or Easement Acquisition

Instream Flow Land or Easement Acquisition
Project IDBPA_2001-021-00_88260
Recovery Domains -
Start Date07/01/2021
End Date06/30/2022
StatusCompleted
Last Edited11/10/2021
 
1 - 1

Description    


Project 2001-021-00:

https://www.cbfish.org/Project.mvc/Display/2001-021-00



Wasco County Soil and Water Conservation District (SWCD) provides local leadership in implementation of several full-scale watershed enhancement projects focused on improving watershed health. Working in close partnership with Natural Resources Conservation Service (NRCS) our teams strength is our ability to develop and implement scientifically sound, economically feasible resource management plans for private landowners.



This project to implement riparian buffer systems in the Mid-Columbia addresses high priority actions identified in the Fifteenmile Sub-basin Plan. It will dedicate 1.0 FTE to provide the technical planning support needed to implement at least 36 riparian buffer system contracts on approximately 872 acres covering an estimated 40 miles of anadromous fish streams as a 3-year goal. Buffer widths will be between 35 and 180 ft. on each side of the stream. Implementation will include prescribed plantings, fencing, and related practices. Actual implementation costs, lease payments, and maintenance costs will be borne by existing U.S. Department of Agriculture (USDA) programs: Conservation Reserve Program (CRP) and Conservation Reserve Enhancement Programs (CREP). Leases will be for 10-15 year periods.



Ten to fifteen (10-15) CCRP/CREP agreements will be signed by landowners annually, committing desired property to CCRP/CREP rules, i.e. shrub/tree/grass planting, weed control, livestock exclusion. Wasco SWCD staff will track contracts to ensure a smooth process between landowners and partner agencies. This tracking entails monitoring the approval process on completed plans through SWCD, NRCS, and FSA County Committee sign-off and Farm Service Agency (FSA) contracting.



This program meets a critical need in Fifteenmile Watershed in particular where existing Oregon Department of Fish and Wildlife (ODFW) riparian lease agreements are expiring. This project f



Contract 88260:

https://www.cbfish.org/Contract.mvc/Summary/88260



Project Map



Worksites

BPA - BPA_2001-021-00_88260-ws-586137: L: 92. Lease Land    


  • Worksite Identifier: BPA - BPA_2001-021-00_88260-ws-586137: L: 92. Lease Land
  • Start Date: 07/01/2021
  • End Date: 09/30/2021
Area Description

Renew CREP Agreement (initiated in prior contract) with Landowners, NRCS, SWCD & FSA, Start of Reach

Additional Detail

Work Statement Element 161535:

https://www.cbfish.org/WorkStatementElement.mvc/Summary/161535



This work element (WE) continues the work initiated in the prior contract (85547 WE: AF). A CREP agreement will be renewed and signed resulting in continued riparian protections.

This riparian protection project is located along the Deschutes River, a direct tributary to the Columbia River which is mapped Essential Salmonid Habitat (ESH) (https://www.streamnet.org).

The project reach is currently enrolled in CREP. Prior restoration activities include riparian fencing, livestock use exclusion, and riparian planting. This buffer contract is eligible to be renewed for an additional 15 years, resulting in continued riparian protections. The process includes assessment of the existing buffer status, updating the conservation plan and CREP agreement, and providing technical assistance to landowners. The landowner is responsible for all implementation activities.

Location Information

  • Basin:
  • Subbasin:
  • Watershed:
  • Subwatershed:
  • State:
  • Recovery Domain:
  • Latitude: 45.528411
  • Longitude: -120.884625

ESU

    No ESU data was found for this worksite.

Map

Photos

Metrics

Metrics
  • C.0 Salmonid Habitat Restoration and AcquisitionY (Y/N)
    •      . . C.10 Land or Easement AcquisitionY (Y/N)
      •      . . . . C.10.a Land acquisition funding 276.94
      •      . . . . C.10.c.1 Acquisition or lease of land, wetland or estuarine area for conservationY (Y/N)

BPA - BPA_2001-021-00_88260-ws-586142: Q: 92. Lease Land    


  • Worksite Identifier: BPA - BPA_2001-021-00_88260-ws-586142: Q: 92. Lease Land
  • Start Date: 07/01/2021
  • End Date: 09/30/2021
Area Description

Renew CREP Agreement (initiated in prior contract) with Landowners, NRCS, SWCD & FSA, Start of Reach

Additional Detail

Work Statement Element 161540:

https://www.cbfish.org/WorkStatementElement.mvc/Summary/161540



This work element (WE) continues the work initiated in the prior contract (85547 WE: AK). A CREP agreement will be renewed and signed resulting in continued riparian protections. A completed water survey form will be uploaded because water rights are associated with the CREP buffer.

This riparian protection project is located along Eightmile Creek, a direct tributary to Fifteenmile Creek which is mapped Essential Salmonid Habitat (ESH) (https://www.streamnet.org). Work Elements P. and Q. are projects that compliment one another. P. is marginal pasture, non-irrigated ground and Q. is the irrigated ground.

The project reach is currently enrolled in CREP. Prior restoration activities include riparian fencing, livestock use exclusion, and riparian planting. This buffer contract is eligible to be renewed for an additional 15 years, resulting in continued riparian protections. The process includes assessment of the existing buffer status, updating the conservation plan and CREP agreement, and providing technical assistance to landowners. The landowner is responsible for all implementation activities.

Location Information

  • Basin:
  • Subbasin:
  • Watershed:
  • Subwatershed:
  • State:
  • Recovery Domain:
  • Latitude: 45.502873
  • Longitude: -121.134459

ESU

    No ESU data was found for this worksite.

Map

Photos

Metrics

Metrics
  • C.0 Salmonid Habitat Restoration and AcquisitionY (Y/N)
    •      . . C.3 Instream Flow ProjectY (Y/N)
      •      . . . . C.3.a Instream Flow Funding 138.47
      •      . . . . C.3.f.1 Water leased or purchasedY (Y/N)
        •      . . . . . . C.3.f.2 Acre feet of water per year purchased/leased24 (Acre feet)
        •      . . . . . . C.3.f.3 cfs (cubic feet per second) of water purchased/leased0 (cfs)
      •      . . C.10 Land or Easement AcquisitionY (Y/N)
        •      . . . . C.10.a Land acquisition funding 138.47
        •      . . . . C.10.c.1 Acquisition or lease of land, wetland or estuarine area for conservationY (Y/N)

BPA - BPA_2001-021-00_88260-ws-586134: K: 92. Lease Land    


  • Worksite Identifier: BPA - BPA_2001-021-00_88260-ws-586134: K: 92. Lease Land
  • Start Date: 07/01/2021
  • End Date: 09/30/2021
Area Description

Renew CREP Agreement (initiated in prior contract) with Landowners, NRCS, SWCD & FSA, Start of Reach

Additional Detail

Work Statement Element 160812:

https://www.cbfish.org/WorkStatementElement.mvc/Summary/160812



This work element (WE) continues the work initiated in the prior contract (85547 WE: AE).

This riparian protection project is located along Wapinitia Creek, a direct tributary to the Deschutes River which is mapped Essential Salmonid Habitat (ESH) (https://www.streamnet.org).

The project reach is currently enrolled in CREP. Prior restoration activities include riparian fencing, livestock use exclusion, and riparian planting. This buffer contract is eligible to be renewed for an additional 15 years, resulting in continued riparian protections. The process includes assessment of the existing buffer status, updating the conservation plan and CREP agreement, and providing technical assistance to landowners. The landowner is responsible for all implementation activities.

There is one man made dam on this tract (predating the existing CREP agreement) and numerous beaver dams throughout Wapinitia. This area has been hit hard by previous drought conditions, while it is typically a very strong, seasonal with annual pockets. The system has both lotic and lentic properties and the buffer greatly benefits both systems. According to ODFW, no known fish barriers exist in this reach. Lower Wapinitia Creek provides off channel refugia for anadromous fish as well as significant biota for all fish species in Wapinitia creek and the Deschutes.

When the Stream is not flowing throughout the channel during summer flows, the buffer encompasses the beaver dams that provide significant habitat for a plethora of species. As can be seen on aerial photos, the riparian areas in this stretch is a significant contrast to the upland habitats providing lentic benefits.

Location Information

  • Basin:
  • Subbasin:
  • Watershed:
  • Subwatershed:
  • State:
  • Recovery Domain:
  • Latitude: 45.109947
  • Longitude: -121.2326

ESU

    No ESU data was found for this worksite.

Map

Photos

Metrics

Metrics
  • C.0 Salmonid Habitat Restoration and AcquisitionY (Y/N)
    •      . . C.10 Land or Easement AcquisitionY (Y/N)
      •      . . . . C.10.a Land acquisition funding 1,384.69
      •      . . . . C.10.c.1 Acquisition or lease of land, wetland or estuarine area for conservationY (Y/N)

BPA - BPA_2001-021-00_88260-ws-586138: M: 92. Lease Land    


  • Worksite Identifier: BPA - BPA_2001-021-00_88260-ws-586138: M: 92. Lease Land
  • Start Date: 07/01/2021
  • End Date: 09/30/2021
Area Description

Renew CREP Agreement (initiated in prior contract) with Landowners, NRCS, SWCD & FSA, Start of Reach

Additional Detail

Work Statement Element 161536:

https://www.cbfish.org/WorkStatementElement.mvc/Summary/161536



This work element (WE) continues the work initiated in the prior contract (85547 WE: AG).

A CREP agreement will be renewed and signed resulting in continued riparian protections.

This riparian protection project is located along Fifteenmile Creek, a direct tributary to the Columbia River which is mapped Essential Salmonid Habitat (ESH) (https://www.streamnet.org). Work Elements M. and N. are projects that compliment one another. M. is the marginal pasture, non-irrigated ground and N. is the irrigated ground.

The project reach is currently enrolled in CREP. Prior restoration activities include riparian fencing, livestock use exclusion, and riparian planting. This buffer contract is eligible to be renewed for an additional 15 years, resulting in continued riparian protections. The process includes assessment of the existing buffer status, updating the conservation plan and CREP agreement, and providing technical assistance to landowners. The landowner is responsible for all implementation activities.

Location Information

  • Basin:
  • Subbasin:
  • Watershed:
  • Subwatershed:
  • State:
  • Recovery Domain:
  • Latitude: 45.446713
  • Longitude: -121.152396

ESU

    No ESU data was found for this worksite.

Map

Photos

Metrics

Metrics
  • C.0 Salmonid Habitat Restoration and AcquisitionY (Y/N)
    •      . . C.10 Land or Easement AcquisitionY (Y/N)
      •      . . . . C.10.a Land acquisition funding 276.94
      •      . . . . C.10.c.1 Acquisition or lease of land, wetland or estuarine area for conservationY (Y/N)

BPA - BPA_2001-021-00_88260-ws-586139: N: 92. Lease Land    


  • Worksite Identifier: BPA - BPA_2001-021-00_88260-ws-586139: N: 92. Lease Land
  • Start Date: 07/01/2021
  • End Date: 09/30/2021
Area Description

Renew CREP Agreement (initiated in prior contract) with Landowners, NRCS, SWCD & FSA, Start of Reach

Additional Detail

Work Statement Element 161537:

https://www.cbfish.org/WorkStatementElement.mvc/Summary/161537



This work element (WE) continues the work initiated in the prior contract (85547 WE: AH). A CREP agreement will be renewed and signed resulting in continued riparian protections. A completed water survey form will be uploaded because water rights are associated with the CREP buffer.

This riparian protection project is located along Fifteenmile Creek, a direct tributary to the Columbia River which is mapped Essential Salmonid Habitat (ESH) (https://www.streamnet.org). Work Elements M. and N. are projects that compliment one another. M. is the marginal pasture, non-irrigated ground and N. is the irrigated ground.

The project reach is currently enrolled in CREP. Prior restoration activities include riparian fencing, livestock use exclusion, and riparian planting. This buffer contract is eligible to be renewed for an additional 15 years, resulting in continued riparian protections. The process includes assessment of the existing buffer status, updating the conservation plan and CREP agreement, and providing technical assistance to landowners. The landowner is responsible for all implementation activities.

Location Information

  • Basin:
  • Subbasin:
  • Watershed:
  • Subwatershed:
  • State:
  • Recovery Domain:
  • Latitude: 45.446713
  • Longitude: -121.152396

ESU

    No ESU data was found for this worksite.

Map

Photos

Metrics

Metrics
  • C.0 Salmonid Habitat Restoration and AcquisitionY (Y/N)
    •      . . C.3 Instream Flow ProjectY (Y/N)
      •      . . . . C.3.a Instream Flow Funding 138.47
      •      . . . . C.3.f.1 Water leased or purchasedY (Y/N)
        •      . . . . . . C.3.f.2 Acre feet of water per year purchased/leased6 (Acre feet)
        •      . . . . . . C.3.f.3 cfs (cubic feet per second) of water purchased/leased0 (cfs)
      •      . . C.10 Land or Easement AcquisitionY (Y/N)
        •      . . . . C.10.a Land acquisition funding 138.47
        •      . . . . C.10.c.1 Acquisition or lease of land, wetland or estuarine area for conservationY (Y/N)

BPA - BPA_2001-021-00_88260-ws-586141: P: 92. Lease Land    


  • Worksite Identifier: BPA - BPA_2001-021-00_88260-ws-586141: P: 92. Lease Land
  • Start Date: 07/01/2021
  • End Date: 09/30/2021
Area Description

Renew CREP Agreement (initiated in prior contract) with Landowners, NRCS, SWCD & FSA, Start of Reach

Additional Detail

Work Statement Element 161539:

https://www.cbfish.org/WorkStatementElement.mvc/Summary/161539



This work element (WE) continues the work initiated in the prior contract (85547 WE: AJ). A CREP agreement will be renewed and signed resulting in continued riparian protections.

This riparian protection project is located along Eightmile Creek, a direct tributary to Fifteenmile Creek which is mapped Essential Salmonid Habitat (ESH) (https://www.streamnet.org). Work Elements P. and Q. are projects that compliment one another. P. is marginal pasture, non-irrigated ground and Q. is the irrigated ground.

The project reach is currently enrolled in CREP. Prior restoration activities include riparian fencing, livestock use exclusion, and riparian planting. This buffer contract is eligible to be renewed for an additional 15 years, resulting in continued riparian protections. The process includes assessment of the existing buffer status, updating the conservation plan and CREP agreement, and providing technical assistance to landowners. The landowner is responsible for all implementation activities.

Location Information

  • Basin:
  • Subbasin:
  • Watershed:
  • Subwatershed:
  • State:
  • Recovery Domain:
  • Latitude: 45.502366
  • Longitude: -121.135333

ESU

    No ESU data was found for this worksite.

Map

Photos

Metrics

Metrics
  • C.0 Salmonid Habitat Restoration and AcquisitionY (Y/N)
    •      . . C.10 Land or Easement AcquisitionY (Y/N)
      •      . . . . C.10.a Land acquisition funding 276.94
      •      . . . . C.10.c.1 Acquisition or lease of land, wetland or estuarine area for conservationY (Y/N)

BPA - BPA_2001-021-00_88260-ws-586140: O: 92. Lease Land    


  • Worksite Identifier: BPA - BPA_2001-021-00_88260-ws-586140: O: 92. Lease Land
  • Start Date: 07/01/2021
  • End Date: 09/30/2021
Area Description

Renew CREP Agreement (initiated in prior contract) with Landowners, NRCS, SWCD & FSA, End of Reach

Additional Detail

Work Statement Element 161538:

https://www.cbfish.org/WorkStatementElement.mvc/Summary/161538



This work element (WE) continues the work initiated in the prior contract (85547 WE: AI). A CREP agreement will be renewed and signed resulting in continued riparian protections.

This riparian protection project is located along Dry Creek, a direct tributary to Fifteenmile Creek which is mapped Essential Salmonid Habitat (ESH) (https://www.streamnet.org). This project is within one mile upstream of the mapped anadromous distribution on Dry Creek. ODFW has indicated that steelhead may occasionally use this reach and that the riparian buffer will contribute to downstream water quality.

The project reach is currently enrolled in CREP. Prior restoration activities include riparian fencing, livestock use exclusion, and riparian planting. This buffer contract is eligible to be renewed for an additional 15 years, resulting in continued riparian protections. The process includes assessment of the existing buffer status, updating the conservation plan and CREP agreement, and providing technical assistance to landowners. The landowner is responsible for all implementation activities.

Location Information

  • Basin:
  • Subbasin:
  • Watershed:
  • Subwatershed:
  • State:
  • Recovery Domain:
  • Latitude: 45.475644
  • Longitude: -121.063352

ESU

    No ESU data was found for this worksite.

Map

Photos

Metrics

Metrics
  • C.0 Salmonid Habitat Restoration and AcquisitionY (Y/N)
    •      . . C.10 Land or Easement AcquisitionY (Y/N)
      •      . . . . C.10.a Land acquisition funding 276.94
      •      . . . . C.10.c.1 Acquisition or lease of land, wetland or estuarine area for conservationY (Y/N)