Cedar Creek Fish Passage Restoration 04
Fish Passage Improvement
|
HWS_12130 | - | 01/03/2005 | 10/07/2009 | Completed | 12/02/2014 | |
| |
Description
In October 2005, Cedar Creek Dam, which provided municipal water supply for the Town of Ione was removed, allowing Cedar Creek to flow freely to the Pend Oreille River for the first time in over 50 years. The project was the result of nearly 5 years of co
Worksites
HWS - HWS_12130-ws-1: Cedar Creek Dam 1
- Worksite Identifier: HWS - HWS_12130-ws-1: Cedar Creek Dam 1
- Start Date:
- End Date:
Location Information
- Basin: 170102
- Subbasin: 17010216
- Watershed: 1701021603
- Subwatershed: 170102160302
- State: WA
- Recovery Domain:
- Latitude: 48.7538043606
- Longitude: -117.441674986
ESU
No ESU data was found for this worksite.
Map
Photos
Metrics
Metrics
- C.0
Salmonid Habitat Restoration and AcquisitionY (Y/N)
- . . C.2
Fish Passage ImprovementY (Y/N)
- . . . . C.2.c.1
Fish passage blockages removed or altered (other than road crossings reported in C.2.f to C.2.i)Y (Y/N)
|
|