Acclimation Pond Modification
Salmonid Hatcheries and Harvest Management
|
CCT 07-4 | - | 10/01/2007 | 04/01/2008 | 2007 | Completed | 06/11/2018 | |
| |
Description
The installation of the smooth walled pipe has been successfully implemented. Photos have been taken to document the completion of the project. This project will minimize the potential harm to released Chinook salmon into the Okanogan River.
Project Benefit
Contribute to increased and sustainable salmon populations by increasing the function and operation of the acclimation pond. This project is part of an overall salmon recovery plan utilizing supplementation.
Funding Details |
PCSRF | $37,999 |
Report Total: | $37,999 |
|
| |
Worksites
20093594
- Worksite Identifier: 20093594
- Start Date:
- End Date:
Area Description
No Area Description data was found for this worksite.
Location Information
- Basin: Upper Columbia
- Subbasin:
- Watershed:
- Subwatershed:
- State: Washington
- Recovery Domain:
- Latitude:
- Longitude:
ESU
- Upper Columbia River Steelhead DPS
Photos
Metrics
Metrics
- D.0
Salmonid Hatcheries and Harvest ManagementY (Y/N)
- . . D.0.a
Hatchery and harvest mgmt. funding 37,999.00
- . . D.1
Hatchery Production ProjectY (Y/N)
- . . . . D.1.a
Hatchery Production Funding 37,999.00
- . . . . D.1.c.1
Hatchery operations - facility or equipmentY (Y/N)
|
|