Mill Creek Restoration Enhancement

Salmonid Habitat Restoration and Acquisition

Project ID2007-1
Recovery DomainsN Central California Coast
Start Date06/01/2007
End Date09/30/2008
Year2007
StatusCompleted
Last Edited01/26/2024
 
1 - 1

Description    


The various stream restoration and enhancement activities described in the proposal were met and even exceeded with the development/enhancement of 5 boulder scour pools and the installation of 9 boulder weirs to direct channel flow tot he center of the channel thus increasing back stability and placing additional rip rap in several corners extending their length and further directing stream flow tot he next corner and reduce scour action along the banks, improving nearly 1/4 mile of stream bank stability and fish habitat.

Project Benefit    


Improvement of existing instream and bank stabilization projects and conditions as well as the protection of past investments within the stream restoration project area.

Accomplishments

Metric Completed Originally
Proposed

Funding Details

SourceFunds
PCSRF$34,000
Report Total:$34,000


Project Map



Worksites

20093583    


  • Worksite Identifier: 20093583
  • Start Date: 06/01/2007
  • End Date: 12/31/2007
Area Description

No Area Description data was found for this worksite.

Location Information

  • Basin: Northern California Coastal (180101)
  • Subbasin:
  • Watershed: Mill Creek
  • Subwatershed:
  • State: California
  • Recovery Domain: N Central California Coast
  • Latitude: 39.788333
  • Longitude: -123.210278

ESU

  • California Coastal Chinook Salmon ESU
  • Central California Coast Steelhead DPS

Map

Photos

Metrics

Metrics
  • C.0 Salmonid Habitat Restoration and AcquisitionY (Y/N)
    •      . . C.0.a Habitat restoration and acquisition funding 34,000.00
    •      . . C.0.b Length of stream treated/protected 2.40
    •      . . C.0.c
      Project identified in a Plan or Watershed Assessment
      1998 Instream Monitoring Inventory and Assessment of Anadromous Habitats - Final Report
    •      . . C.0.d.1 Project Monitoring (LOV)
    •      . . C.0.d.2 Monitoring Location (LOV)
    •      . . C.0.d.3
      Monitoring text (from Phase I)
      Same as above
    •      . . C.11 Site maintenance projectY (Y/N)
      •      . . . . C.11.a Site maintenance funding 34,000.00
      •      . . . . C.11.b.1 Stream or streambank maintainedY (Y/N)
        •      . . . . . . C.11.b.2 Miles of streambank maintained 2.30