Klamath Basin Specialist
Salmonid Restoration Planning and Assessments
|
FSH_05_KBS | N CA - S Oregon | 12/30/2006 | 12/30/2006 | 2005 | Completed | 01/14/2025 | |
| |
Description
The Klamath Basin Specialist provided the Hoopa Valley Tribal Fisheries Department, the Office of Tribal Attorney, and the Tribes outside attorneys with valuable technical advice and oversight in a number of areas regarding the Tribes fishing rights. Areas of focus included the relicensing of the dams on the Klamath River and issues surrounding the implementation of the PCFFA settlement agreement.
Project goal Klamath Basin Specialist (Consultant) provided technical services to the Hoopa Valley Tribe (Tribe). The near-term goals are for Klamath Basin Specialist are to: • provide Tribal fisheries, policy and legal staff with technical assistance in Klamath River Hydroelectric Project relicensing proceedings, • help the Tribe protect its interests under the PCFFA Settlement Agreement, and • identify appropriate goals and activities related to its fisheries and aquatic resources based on a comprehensive needs assessment, along with recommendations for technical assistance that might be required during the foreseeable future.
Project Benefit
This project will provide informed policy guidance for Tribal Officials in guiding future efforts to protect the fisheries resource of the Hoopa Valley Tribe.
Funding Details |
PCSRF | $25,000 |
Report Total: | $25,000 |
|
| |
Worksites
20108179
- Worksite Identifier: 20108179
- Start Date:
- End Date:
Area Description
No Area Description data was found for this worksite.
Location Information
- Basin: Klamath (180102)
- Subbasin: Trinity (18010211)
- Watershed:
- Subwatershed:
- State: California
- Recovery Domain: N CA - S Oregon
- Latitude: 41.089
- Longitude: -123.70305
ESU
No ESU data was found for this worksite.
Map
Photos
Metrics
Metrics
- B.0
Salmonid Restoration Planning and AssessmentsY (Y/N)
- . . B.0.a
Planning And Assessment Funding 25,000.00
- . . B.0.b.1
Area Encompassed .0
- . . B.1
Restoration Planning And CoordinationY (Y/N)
- . . . . B.1.a
Planning and Coordination funding 25,000.00
- . . . . B.1.b.6
Support to local entities or agenciesY (Y/N)
- . . . . . . B.1.b.6.a
Name of plan developed or implemented | |
Klamath Hydropower Settlement Agreement. Klamath Basin Restoration Agreement. |
- . . . . . . B.1.b.6.b
Description and scope of the plan developed/implemented | |
Negotiated plan to remove dams, allot water to agriculture, and protect fisheries in the Klamath Basin. |
|
|