Salmon Habitat Restoration Needs Inventory and Project Identification

Salmonid Restoration Planning and Assessments

Restoration Planning And Coordination
Project ID047 05 CW
Recovery DomainsSnake River
Start Date01/01/2006
End Date10/31/2006
Year2005
StatusCompleted
Last Edited01/14/2025
 
1 - 1

Description    


This project was completed as proposed; it identified and prioritized mitigation and restoration projects-using publicly available data- relating to endangered salmonid species, in the Clearwater basin on private lands. Several mitigation projects proposals were developed as a result of this effort. Salmon Habitat and Restoration worksites identified by this project will be completed as a follow up to this project. The approved project number is 047 05x CW funded from the 2005 grant appropriation.

Project Benefit    


This project is designed to identify and prioritize mitigation and restoration projects that can have a direct beneficial impact on endangered salmonid species pm private lands within the Clearwater basin. This project will also result in development of specific mitigation projects proposals for future funding. Ultimately, implementation of these projects is expected to result in enhanced fish passage, reduction of sediment delivery to streams, improved riparian vegetation to meet shade and future large wood recruitment needs, and addition of in-stream structures to enhance habitat.

Accomplishments

Metric Completed Originally
Proposed

Funding Details

SourceFunds
PCSRF$7,514
State$2,505
Report Total:$10,019


Project Map



Worksites

1 of 1    


  • Worksite Identifier: 1 of 1
  • Start Date: 01/01/2006
  • End Date: 10/31/2006
Area Description

No Area Description data was found for this worksite.

Location Information

  • Basin: Clearwater (170603)
  • Subbasin: Clearwater (17060306)
  • Watershed:
  • Subwatershed:
  • State: Idaho
  • Recovery Domain: Snake River
  • Latitude: 46.9225
  • Longitude: -116.4394

ESU

  • Snake River Basin Steelhead DPS

Map

Photos

Metrics

Metrics
  • B.0 Salmonid Restoration Planning and AssessmentsY (Y/N)
    •      . . B.0.a Planning And Assessment Funding 10,019.00
    •      . . B.0.b.1 Area Encompassed 15,000.0
    •      . . B.1 Restoration Planning And CoordinationY (Y/N)
      •      . . . . B.1.a Planning and Coordination funding 10,019.00
      •      . . . . B.1.b.12 Developing restoration/action planY (Y/N)
        •      . . . . . . B.1.b.12.a
          Name of plan developed
          Colla, 2007, List of Projects, Colla, Northwest Management, Moscow, Idaho.
        •      . . . . . . B.1.b.12.b
          Description and scope of the plan developed
          A list of projects to identify and prioritize mitigation and restoration projects.