Upper Klickitat River In-Channel and Floodplain Enhancement Project
Salmonid Habitat Restoration and Acquisition
|
2005-4-04 | Middle Columbia River | 02/01/2006 | 05/31/2009 | 2005 | Completed | 01/26/2024 | |
| |
Description
LWD harvest and stockpiling occurred at sites 3 and 4 during the summer of 2008. An administrative mishandling of the tribal hydraulics permit application precluded issuance of the permit during the seasonal in-water work period. In-water work was not completed prior to 5/31/09 and so arrangements were made to transfer grant money to the materials line item so that cable and clamps could be purchased. The cable and clamps will be used to secure LWD jams when they are constructed at some point in the future. These materials were purchased in May of 2009. In addition, the remaining balance of the grant was transferred to PCSRF FY05 Phase IV Equipment Acquisition project.
Project Benefit
The proposed actions target mid-Columbia steelhead (Endangered Species Act-Threatened) and spring Chinook salmon (Washington Department of Fish and Wildlife-Depressed). Quantity and quality of juvenile rearing and adult holding habitat will be improved considerably. Benefits are also expected for spawning habitat as a result of improved substrate sorting and reduced fine sediment introduction.
Accomplishments
Instream Habitat |
Stream Miles Treated |
.00 |
.61 |
Riparian Habitat |
Stream Miles Treated |
.00 |
.61 |
Acres Treated |
.0 |
2.1 |
Funding Details |
PCSRF | $98,607 |
Report Total: | $98,607 |
|
| |
Worksites
1.Upper Klickitat River RM70.7
- Worksite Identifier: 1.Upper Klickitat River RM70.7
- Start Date: 02/01/2006
- End Date: 11/07/2007
Area Description
No Area Description data was found for this worksite.
Location Information
- Basin: Middle Columbia (170701)
- Subbasin: Klickitat
- Watershed: 170701060103
- Subwatershed:
- State: Washington
- Recovery Domain: Middle Columbia River
- Latitude: 46.31839
- Longitude: -121.26012
ESU
- Mid-Columbia River Spring-run Chinook Salmon ESU
- Middle Columbia River Steelhead DPS
Map
Photos
Metrics
Metrics
- C.0
Salmonid Habitat Restoration and AcquisitionY (Y/N)
- . . C.0.a
Habitat restoration and acquisition funding 34,000.00
- . . C.0.b
Length of stream treated/protected .00
- . . C.0.c
Project identified in a Plan or Watershed Assessment | |
Unknown |
- . . C.0.d.1
Project Monitoring (LOV)
- . . C.0.d.2
Monitoring Location (LOV)
- . . C.0.d.3
Monitoring text (from Phase I) | |
No monitoring has or will be conducted due to the fact that no in-stream work was performed as a part of this project. |
- . . C.4
Instream Habitat ProjectY (Y/N)
- . . . . C.4.a
Instream Habitat Funding 20,000.00
- . . . . C.4.b
Total length of instream habitat treated .00
- . . . . C.4.e.1
Streambank stabilization Y (Y/N)
- . . . . . . C.4.e.2
Material Used For Streambank Stabilization (LOV)
- . . . . . . C.4.e.3
Miles of streambank stabilized .00
- . . C.5
Riparian Habitat ProjectY (Y/N)
- . . . . C.5.a
Riparian Habitat Funding 14,000.00
- . . . . C.5.b.1
Total riparian miles streambank treated .00
- . . . . C.5.b.2
Total Riparian Acres Treated .0
- . . . . C.5.h.1
Riparian plant removal/controlY (Y/N)
- . . . . . . C.5.h.2
Species of plants treated/removed in riparian | |
none |
- . . . . . . C.5.h.3
Acres of riparian treated for plant removal/control .0
3.Upper Klickitat River RM74.4
- Worksite Identifier: 3.Upper Klickitat River RM74.4
- Start Date: 02/01/2006
- End Date: 11/07/2007
Area Description
No Area Description data was found for this worksite.
Location Information
- Basin: Middle Columbia (170701)
- Subbasin: Klickitat
- Watershed:
- Subwatershed:
- State: Washington
- Recovery Domain: Middle Columbia River
- Latitude: 46.34248
- Longitude: -121.20675
ESU
- Mid-Columbia River Spring-run Chinook Salmon ESU
- Middle Columbia River Steelhead DPS
Map
Photos
Metrics
Metrics
- C.0
Salmonid Habitat Restoration and AcquisitionY (Y/N)
- . . C.0.a
Habitat restoration and acquisition funding 33,000.00
- . . C.0.b
Length of stream treated/protected .00
- . . C.0.c
Project identified in a Plan or Watershed Assessment | |
Yakama Indian Nation, Fisheries Dept. "Klickitat River Salmon Recovery Plan, Draft", Toppenish, WA: 2005
CRITFC, "Wy-Kan-Ish-Mi Wa-Kish-Wit", Portland,OR: 2000 |
- . . C.0.d.1
Project Monitoring (LOV)
- . . C.0.d.2
Monitoring Location (LOV)
- . . C.0.d.3
Monitoring text (from Phase I) | |
All three project sites occur within a 5-mile reach:
-that has been surveyed annually for steelhead and spring Chinook spawning for the last 3 years. Surveys are expected to continue indefinitely.
-that contains four TFW habitat segments which are intended to be resurveyed every 5 to 7 years. Snorkel surveys were completed for each segment.
At each site:
-Snorkel surveys will be conducted prior to implementation.
-Vegetation survival will be monitored following implementation with a 50% target.
-Profile and cross-section surveys will be completed prior to implementation.
-Active-channel substrate will be characterized prior to implementation.
-An as-built profile survey will be completed. Cross-sections will be surveyed as time allows.
|
- . . C.4
Instream Habitat ProjectY (Y/N)
- . . . . C.4.a
Instream Habitat Funding 20,000.00
- . . . . C.4.b
Total length of instream habitat treated .00
- . . . . C.4.e.1
Streambank stabilization Y (Y/N)
- . . . . . . C.4.e.2
Material Used For Streambank Stabilization (LOV)
- . . . . . . C.4.e.3
Miles of streambank stabilized .00
- . . C.5
Riparian Habitat ProjectY (Y/N)
- . . . . C.5.a
Riparian Habitat Funding 13,000.00
- . . . . C.5.b.1
Total riparian miles streambank treated .00
- . . . . C.5.b.2
Total Riparian Acres Treated .0
- . . . . C.5.h.1
Riparian plant removal/controlY (Y/N)
- . . . . . . C.5.h.2
Species of plants treated/removed in riparian | |
none |
- . . . . . . C.5.h.3
Acres of riparian treated for plant removal/control .0
2.Upper Klickitat River RM73.9
- Worksite Identifier: 2.Upper Klickitat River RM73.9
- Start Date: 02/01/2006
- End Date: 11/07/2007
Area Description
No Area Description data was found for this worksite.
Location Information
- Basin: Middle Columbia (170701)
- Subbasin: Klickitat
- Watershed: 1707010601
- Subwatershed:
- State: Washington
- Recovery Domain: Middle Columbia River
- Latitude: 46.33808
- Longitude: -121.21411
ESU
- Mid-Columbia River Spring-run Chinook Salmon ESU
- Middle Columbia River Steelhead DPS
Map
Photos
Metrics
Metrics
- C.0
Salmonid Habitat Restoration and AcquisitionY (Y/N)
- . . C.0.a
Habitat restoration and acquisition funding 31,607.00
- . . C.0.b
Length of stream treated/protected .00
- . . C.0.c
Project identified in a Plan or Watershed Assessment | |
Yakama Indian Nation, Fisheries Dept. "Klickitat River Salmon Recovery Plan, Draft", Toppenish, WA: 2005 |
- . . C.0.d.1
Project Monitoring (LOV)
- . . C.0.d.2
Monitoring Location (LOV)
- . . C.0.d.3
Monitoring text (from Phase I) | |
All three project sites occur within a 5-mile reach:
-that has been surveyed annually for steelhead and spring Chinook spawning for the last 3 years. Surveys are expected to continue indefinitely.
-that contains four TFW habitat segments which are intended to be resurveyed every 5 to 7 years. Snorkel surveys were completed for each segment.
At each site:
-Snorkel surveys will be conducted prior to implementation.
-Vegetation survival will be monitored following implementation with a 50% target.
-Profile and cross-section surveys will be completed prior to implementation.
-Active-channel substrate will be characterized prior to implementation.
-An as-built profile survey will be completed. Cross-sections will be surveyed as time allows.
|
- . . C.4
Instream Habitat ProjectY (Y/N)
- . . . . C.4.a
Instream Habitat Funding 20,000.00
- . . . . C.4.b
Total length of instream habitat treated .00
- . . . . C.4.e.1
Streambank stabilization Y (Y/N)
- . . . . . . C.4.e.2
Material Used For Streambank Stabilization (LOV)
- . . . . . . C.4.e.3
Miles of streambank stabilized .00
- . . C.5
Riparian Habitat ProjectY (Y/N)
- . . . . C.5.a
Riparian Habitat Funding 11,607.00
- . . . . C.5.b.1
Total riparian miles streambank treated .00
- . . . . C.5.b.2
Total Riparian Acres Treated .0
- . . . . C.5.h.1
Riparian plant removal/controlY (Y/N)
- . . . . . . C.5.h.2
Species of plants treated/removed in riparian | |
None |
- . . . . . . C.5.h.3
Acres of riparian treated for plant removal/control .0
|
|