Doe Creek Culvert Removal

Salmonid Habitat Restoration and Acquisition

Fish Passage Improvement Instream Habitat
Project IDOWEB 207-345-5607
Recovery DomainsSnake River
Start Date06/04/2007
End Date05/22/2008
Year2006
StatusCompleted
Last Edited06/24/2025
 
1 - 1

Description    


This project installed a rock/boulder V structure; modified or created a main stream channel; placed instream anchored habitat structures; placed large wood instream; replaced culverts or structures with open bottom arch culverts.

Project Benefit    


OWRI: improve/increase fish passage; improve/increase stream interaction with floodplain; improve/increase stream spawning habitat; improve/increase stream structure & complexity;

Accomplishments

Metric Completed Originally
Proposed
Instream Habitat
  Stream Miles Treated .05
Fish Passage
  Barriers Removed
  Miles Opened .50

Funding Details

SourceFunds
State$102,500
Other$51,323
In-Kind Other$9,400
Report Total:$163,223


Project Map



Worksites

20070356    


  • Worksite Identifier: 20070356
  • Start Date:
  • End Date:
Area Description

No Area Description data was found for this worksite.

Location Information

  • Basin: Lower Snake (170601)
  • Subbasin: Lower Grande Ronde (17060106)
  • Watershed:
  • Subwatershed:
  • State: Oregon
  • Recovery Domain: Snake River
  • Latitude: 45.7474189
  • Longitude: -117.02291095

ESU

  • Snake River Basin Steelhead DPS

Map

Photos

Metrics

Metrics
  • C.0 Salmonid Habitat Restoration and AcquisitionY (Y/N)
    •      . . C.0.a Habitat restoration and acquisition funding 163,223.00
    •      . . C.0.b Length of stream treated/protected .05
    •      . . C.0.c
      Project identified in a Plan or Watershed Assessment
      Upper Joseph Creek Watershed Assessment
    •      . . C.0.d.1 Project Monitoring (LOV)
    •      . . C.0.d.2 Monitoring Location (LOV)
    •      . . C.2 Fish Passage ImprovementY (Y/N)
      •      . . . . C.2.a Fish Passage Funding 152,085.00
      •      . . . . C.2.b.1 Length of stream made accessible .50
      •      . . . . C.2.b.3 Type of blockage/barrier (LOV)
      •      . . . . C.2.b.4 Number of blockages/impediments/barriers impeding passage 1
      •      . . . . C.2.f.1 Culvert installed or improved at road stream crossingY (Y/N)
        •      . . . . . . C.2.f.2 Number of culverts installed or improved 1
        •      . . . . . . C.2.f.3 Miles of stream made accessible by culvert installation/upgrade .50
      •      . . C.4 Instream Habitat ProjectY (Y/N)
        •      . . . . C.4.a Instream Habitat Funding 11,138.00
        •      . . . . C.4.b Total length of instream habitat treated .05
        •      . . . . C.4.c.1 Channel reconfiguration and connectivityY (Y/N)
          •      . . . . . . C.4.c.2 Type of change to channel configuration and connectivity (LOV)
          •      . . . . . . C.4.c.3 Miles of stream treated for channel reconfiguration and connectivity .04
          •      . . . . . . C.4.c.4 Miles of off-channel stream created through channel reconfiguration and connectivity .00
          •      . . . . . . C.4.c.6 Instream pools created/added through channel reconfiguration and connectivity 0
        •      . . . . C.4.d.1 Channel structure placementY (Y/N)
          •      . . . . . . C.4.d.2 Material used for channel structure (LOV)
          •      . . . . . . C.4.d.3 Miles of stream treated through channel structure placement .05
          •      . . . . . . C.4.d.7 Number of structures placed in channel 4