19-1477 P | Upper Columbia River | 12/12/2019 | 03/18/2022 | 2019 | Completed | 01/14/2025 | |
| |
Description
The project completed conceptual and preliminary designs (including basis of design report, construction cost estimate, hydraulic modeling, etc.) for an effort to better connect an approximately 9-acre floodplain surface, construct approximately 2,500 ft of side channel habitats, and add in-stream structure between approximately RM 4.0 and 4.4 on Peshastin Creek. The designs lay the groundwork for a future restoration project to provide off-channel habitats and enhance in-stream habitats primarily to benefit juvenile Chinook and steelhead rearing.
Project Benefit
To develop a preliminary design for a off-channel restoration alternative to provide critical juvenile Chinook and steelhead rearing habitat.
Funding Details |
PCSRF | $79,208 |
Other | $19,802 |
Report Total: | $99,010 |
|
| |
Worksites
1-Peshastin Side Channel RM 4
- Worksite Identifier: 1-Peshastin Side Channel RM 4
- Start Date:
- End Date:
Area Description
No Area Description data was found for this worksite.
Location Information
- Basin: Upper Columbia (170200)
- Subbasin: Wenatchee (17020011)
- Watershed: Peshastin Creek (1702001105)
- Subwatershed: Lower Peshastin Creek (170200110503)
- State: Washington
- Recovery Domain: Upper Columbia River
- Latitude: 47.51820564
- Longitude: -120.62539229
ESU
- Upper Columbia River Steelhead DPS
- Upper Columbia River Spring-run Chinook Salmon ESU
Map
Photos
Metrics
Metrics
- B.0
Salmonid Restoration Planning and AssessmentsY (Y/N)
- . . B.0.a
Planning And Assessment Funding 99,010.00
- . . B.0.b.1
Area Encompassed 8.9
- . . B.0.b.2
Stream Miles Affected .43
- . . B.1
Restoration Planning And CoordinationY (Y/N)
- . . . . B.1.a
Planning and Coordination funding 99,010.00
- . . . . B.1.b.11
Engineering/design work for restoration projectsY (Y/N)
- . . . . . . B.1.b.11.a
Name of plan implemented | |
Interfluve. 2010. Lower Peshastin Creek Tributary and Reach Assessment. Wenatchee Subbasin, Chelan County, WA. Prepared for Yakama Nation Fisheries Toppenish, WA June. |
- . . . . . . B.1.b.11.b
Description and scope of the plan implemented | |
The project is identified in Upper Columbia Spring Chinook Salmon and Steelhead Recovery Plan (August 2007). Peshastin Creek is identified as a Category 2 Assessment Unit. Recommendations are to re-establish connectivity throughout the assessment unit by removing, replacing, or fixing; artificial barriers; use practical and feasible means to increase stream flows (within the natural hydrologic; regime and existing water rights) in Peshastin Creek; reduce water temperatures by increasing stream flows and restoring riparian vegetation along the stream. Increase habitat diversity and quantity by restoring riparian vegetation, adding instream
structures and large woody debris, and reconnecting side channels and the floodplain with the stream (page 207, lines 17-18) |
|
|