Strait of Juan de Fuca IMW Restoration Project
Salmonid Habitat Restoration and Acquisition
|
16-1427 R | - | 12/08/2016 | 12/31/2021 | 2016 | Completed | 05/01/2025 | |
| |
Description
This project involved restoration actions within the Strait of Juan de Fuca region Intensively Monitored Watershed Project (IMW). IMW is a statewide effort to evaluate the effects of watershed restoration on habitat and salmon abundance. Within the Strait complex, East Twin River and Deep Creek are treatment sites, while the West Twin River is a control watershed. Watershed restoration was initiated in Deep Creek in 1998 and in the East Twin River in 2000. This project completed watershed restoration treatments by placing large wood in complex assemblages using a heavy lift helicopter during the summers of 2019 and 2020. Wood placement was designed to improve habitat conditions and restore floodplain connectivity in the lower portions of both watersheds. Wood was be placed in complex logs at 12 sites in both lower Deep Creek, and East Twin River. Treatments were designed to improve over-winter habitat for coho salmon, improve summer habitat for steelhead and coho, and to improve spawning habitat for multiple species including coho, steelhead, chum, and cutthroat.
Project Benefit
Install large woody debris to improve over-winter habitat for coho salmon, improve summer habitat for steelhead and coho, and to improve spawning habitat for multiple species including coho, steelhead, chum, and cutthroat.
Accomplishments
Instream Habitat |
Stream Miles Treated |
2.40 |
2.70 |
Funding Details |
PCSRF | $625,546 |
Report Total: | $625,546 |
|
| |
Worksites
2-East Twin
- Worksite Identifier: 2-East Twin
- Start Date:
- End Date:
Area Description
No Area Description data was found for this worksite.
Location Information
- Basin: Puget Sound (171100)
- Subbasin:
- Watershed:
- Subwatershed:
- State: Washington
- Recovery Domain:
- Latitude: 48.14730876
- Longitude: -123.93546737
ESU
- Olympic Peninsula Coho Salmon ESU
- Pacific Coast Chum Salmon ESU
- Olympic Peninsula Steelhead DPS
Map
Photos
Metrics
Metrics
- C.0
Salmonid Habitat Restoration and AcquisitionY (Y/N)
- . . C.0.a
Habitat restoration and acquisition funding 248,639.00
- . . C.0.b
Length of stream treated/protected 1.00
- . . C.0.c
Project identified in a Plan or Watershed Assessment | |
|
- . . C.0.d.1
Project Monitoring (LOV)
- . . C.0.d.2
Monitoring Location (LOV)
- . . C.4
Instream Habitat ProjectY (Y/N)
- . . . . C.4.a
Instream Habitat Funding 248,639.00
- . . . . C.4.b
Total length of instream habitat treated 1.00
- . . . . C.4.d.1
Channel structure placementY (Y/N)
- . . . . . . C.4.d.2
Material used for channel structure (LOV)
- . . . . . . C.4.d.3
Miles of stream treated through channel structure placement 1.00
- . . . . . . C.4.d.4
Acres of streambed treated through channel structure placement 2.0
- . . . . . . C.4.d.5
Pools expected to be created through channel structure placement 10
- . . . . . . C.4.d.7
Number of structures placed in channel 12
1-Deep Creek
- Worksite Identifier: 1-Deep Creek
- Start Date:
- End Date:
Area Description
No Area Description data was found for this worksite.
Location Information
- Basin: Puget Sound (171100)
- Subbasin:
- Watershed:
- Subwatershed:
- State: Washington
- Recovery Domain:
- Latitude: 48.16350525
- Longitude: -124.03177243
ESU
- Olympic Peninsula Coho Salmon ESU
- Pacific Coast Chum Salmon ESU
Map
Photos
Metrics
Metrics
- C.0
Salmonid Habitat Restoration and AcquisitionY (Y/N)
- . . C.0.a
Habitat restoration and acquisition funding 376,907.22
- . . C.0.b
Length of stream treated/protected 1.40
- . . C.0.c
Project identified in a Plan or Watershed Assessment | |
|
- . . C.0.d.1
Project Monitoring (LOV)
- . . C.0.d.2
Monitoring Location (LOV)
- . . C.4
Instream Habitat ProjectY (Y/N)
- . . . . C.4.a
Instream Habitat Funding 376,907.22
- . . . . C.4.b
Total length of instream habitat treated 1.40
- . . . . C.4.d.1
Channel structure placementY (Y/N)
- . . . . . . C.4.d.2
Material used for channel structure (LOV)
- . . . . . . C.4.d.3
Miles of stream treated through channel structure placement 1.40
- . . . . . . C.4.d.4
Acres of streambed treated through channel structure placement .5
- . . . . . . C.4.d.5
Pools expected to be created through channel structure placement 10
- . . . . . . C.4.d.7
Number of structures placed in channel 24
|
|