Entiat 4.6 (1D Reach) Prel. Design

Salmonid Restoration Planning and Assessments

Restoration Planning And Coordination
Project ID22-1502 P
Recovery DomainsUpper Columbia River
Start Date09/22/2022
End Date12/31/2024
Year2022
StatusOngoing
Last Edited01/14/2025
 
1 - 1

Description    


This is a preliminary design phase project. The project will aim to address raising temperatures and increased sediment inputs into the Mills 05 Reach of the Entiat River. Water temperature issues will be addressed through enhancing existing riparian habitat along vegetated banks and restoring riparian corridors along cleared sections of bank. Increased sedimentation will be addressed by the addition of Engineered Log Jams (ELJ). The design phase of this project will identify the location and type of ELJ structures that would provide the greatest benefit for redirected stream flow and bank protection, for bank sections that are currently experiencing increased erosion rates. Results of the project would provide a benefit to Steelhead and Spring Chinook populations. Bureau of Reclamation Lower Entiat Reach Assessment identified the Mills 05 Reach to support all life stages of Steelhead. Steelhead spawning, fry and smolt received medium rankings and Summer and Winter Rearing was identified as High. Spring Chinook Winter Rearing was classified as High. Lower instream temperatures will result from increased quality and quantity of riparian vegetation along the banks and placement of ELJ structures will aid in lower total suspended solids and sediments through reduction of bank erosion.

Project Benefit    


The goals of this project are to develop preliminary design elements that will provide increased shading to the 1D reach of the Entiat River and increase habitat complexity and diversity for steelhead spawning and juvenile rearing and holding for steelhead and chinook salmon.

Accomplishments

Metric Completed Originally
Proposed

Funding Details

SourceFunds
PCSRF$128,500
Other$22,750
Report Total:$151,250


Project Map



Worksites

1-Left and Right Bank Entiat     


  • Worksite Identifier: 1-Left and Right Bank Entiat
  • Start Date:
  • End Date:
Area Description

No Area Description data was found for this worksite.

Location Information

  • Basin: Upper Columbia (170200)
  • Subbasin: Upper Columbia-Entiat (17020010)
  • Watershed: Entiat River (1702001002)
  • Subwatershed: Mills Creek-Entiat River (170200100209)
  • State: Washington
  • Recovery Domain: Upper Columbia River
  • Latitude: 47.67363253
  • Longitude: -120.31009401

ESU

  • Upper Columbia River Spring-run Chinook Salmon ESU
  • Upper Columbia River Steelhead DPS

Map

Photos

Metrics

Metrics
  • B.0 Salmonid Restoration Planning and AssessmentsY (Y/N)
    •      . . B.0.a Planning And Assessment Funding
    •      . . B.0.b.1 Area Encompassed
    •      . . B.0.b.2 Stream Miles Affected
    •      . . B.1 Restoration Planning And CoordinationY (Y/N)
      •      . . . . B.1.a Planning and Coordination funding
      •      . . . . B.1.b.11 Engineering/design work for restoration projectsY (Y/N)
        •      . . . . . . B.1.b.11.a
          Name of plan implemented
        •      . . . . . . B.1.b.11.b
          Description and scope of the plan implemented