Restore Lower Peshastin Creek Ph 2 Final Design

Salmonid Restoration Planning and Assessments

Restoration Planning And Coordination
Project ID21-1179 P
Recovery DomainsUpper Columbia River
Start Date09/23/2021
End Date11/30/2023
Year2021
StatusCompleted
Last Edited01/14/2025
 
1 - 1

Description    


With funding from the SRFB Cascade Fisheries and our consulting engineers at Natural Systems Design were able to complete the final design for the Lower Peshastin Creek project. Final hydraulic modeling results, construction cost estimates and the final design can be found in our Basis of Design Report (attached in PRISM).

Project Benefit    


improve habitat quality and quantity for natal and non-natal juvenile and adult salmonids and to emulate natural processes in Lower Peshastin Cr

Accomplishments

Metric Completed Originally
Proposed

Funding Details

SourceFunds
PCSRF$127,273
State$26,557
Other$70,012
Report Total:$223,842


Project Map



Worksites

1-Lower Peshastin Creek    


  • Worksite Identifier: 1-Lower Peshastin Creek
  • Start Date:
  • End Date:
Area Description

No Area Description data was found for this worksite.

Location Information

  • Basin: Upper Columbia (170200)
  • Subbasin: Wenatchee (17020011)
  • Watershed: Peshastin Creek (1702001105)
  • Subwatershed: Lower Peshastin Creek (170200110503)
  • State: Washington
  • Recovery Domain: Upper Columbia River
  • Latitude: 47.55710112
  • Longitude: -120.57657419

ESU

  • Upper Columbia River Spring-run Chinook Salmon ESU
  • Upper Columbia River Steelhead DPS

Map

Photos

Metrics

Metrics
  • B.0 Salmonid Restoration Planning and AssessmentsY (Y/N)
    •      . . B.0.a Planning And Assessment Funding 223,842.00
    •      . . B.0.b.1 Area Encompassed 5.0
    •      . . B.0.b.2 Stream Miles Affected .50
    •      . . B.1 Restoration Planning And CoordinationY (Y/N)
      •      . . . . B.1.a Planning and Coordination funding 223,842.00
      •      . . . . B.1.b.11 Engineering/design work for restoration projectsY (Y/N)
        •      . . . . . . B.1.b.11.a
          Name of plan implemented
          UC Spring Chinook and Steelhead Recovery Plan
        •      . . . . . . B.1.b.11.b
          Description and scope of the plan implemented
          Lower Peshastin Creek is a Tier 2 restoration priority for Spring Chinook and Steelhead and Tier 3 for bull trout