Tumalum Creek LTPBR Phase 3
Salmonid Habitat Restoration and Acquisition
|
| 21-1007 R | | Snake River | | 09/23/2021 | | 01/31/2024 | | 2021 | | Completed | | 05/12/2026 | | |
| |
Description
A total of 93 LTPBR structures were built in phase 3 as well as maintenance of existing structures in Phases 1 & 2. We built 25 beaver dam analogs (BDAs), 14 post-assisted log structures, 60log jams, and maintained existing structures. In particular, we built up 8 BDAs by making them taller and wider in order to create larger ponds for releasing more beaver in future phases. We were successful in creating ~ 3 foot deep ponds upstream of 6 BDAs. We also created numerous smaller ponds to help beaver have temporary cover (and hopefully the beaver will increase the size of these ponds). We noted large numbers of juvenile steelhead in these all the ponds that we built. We also took extra precautions to build secondary dams downstream of large BDAs to facilitate upstream and downstream migration of juvenile and adult steelhead.
Project Benefit
The overall goals have not changed with the purpose of promoting self-sustaining, natural stream processes that improve spawning and rearing habitat for Snake River Steelhead through re-establishment of beaver populations and installation of BDAs and PALS in Tumalum Creek.
Accomplishments
| Instream Habitat |
| Stream Miles Treated |
1.00 |
1.00 |
Funding Details |
| State | $145,500 |
| In-Kind Other | $26,455 |
| Report Total: | $171,955 |
|
| |
Worksites
1-Middle Tumalum Creek
- Worksite Identifier: 1-Middle Tumalum Creek
- Start Date:
- End Date:
Area Description
No Area Description data was found for this worksite.
Location Information
- Basin: Lower Snake (170601)
- Subbasin:
- Watershed:
- Subwatershed:
- State:
- Recovery Domain: Snake River
- Latitude: 46.33847586
- Longitude: -117.62490454
ESU
- Snake River Basin Steelhead DPS
Map
Photos
Metrics
Metrics
- C.0
Salmonid Habitat Restoration and AcquisitionY (Y/N)
- . . C.0.a
Habitat restoration and acquisition funding 171,954.95
- . . C.0.b
Length of stream treated/protected 1.00
- . . C.0.c
| Project identified in a Plan or Watershed Assessment | |
|
- . . C.0.d.1
Project Monitoring (LOV)
- . . C.0.d.2
Monitoring Location (LOV)
- . . C.4
Instream Habitat ProjectY (Y/N)
- . . . . C.4.a
Instream Habitat Funding 171,954.95
- . . . . C.4.b
Total length of instream habitat treated 1.00
- . . . . C.4.d.1
Channel structure placementY (Y/N)
- . . . . . . C.4.d.2
Material used for channel structure (LOV)
- . . . . . . C.4.d.3
Miles of stream treated through channel structure placement 1.00
- . . . . . . C.4.d.5
Pools expected to be created through channel structure placement 15
- . . . . . . C.4.d.7
Number of structures placed in channel 93
- . . . . C.4.h.1
BeaversY (Y/N)
- . . . . . . C.4.h.2
Number of beavers introduced 0
|
|