| 21-1139 P | | Lower Columbia River | | 09/23/2021 | | 09/23/2023 | | 2021 | | Completed | | 05/12/2026 | | |
| |
Description
The project was a design only project to address fish passage through a tide gate located under Oneida Road adjacent to Deep River in Wahkiakum County. The RCO requested that the project include consideration for two adjacent tide gates including one managed by the Washington State Department of Fish and Wildlife and another managed by the Columbia Land Trust.
Project Benefit
The projects goal is to evaluate a tide gate and work through the design process outlined in the RCO handbook to design and permit a project will improve fish passage through the crossing and restore connectivity to lower Deep River. The desired future conditions is a fish friendly structure with improved connectivity.
Funding Details |
| PCSRF | $6,923 |
| Other | $1,402 |
| Report Total: | $8,326 |
|
| |
Worksites
1-Ervest Tide gate
- Worksite Identifier: 1-Ervest Tide gate
- Start Date:
- End Date:
Area Description
No Area Description data was found for this worksite.
Location Information
- Basin: Lower Columbia (170800)
- Subbasin:
- Watershed:
- Subwatershed:
- State:
- Recovery Domain: Lower Columbia River
- Latitude: 46.31024173
- Longitude: -123.71662381
ESU
- Lower Columbia River Coho Salmon ESU
- Columbia River Chum Salmon ESU
Map
Photos
Metrics
Metrics
- B.0
Salmonid Restoration Planning and AssessmentsY (Y/N)
- . . B.0.a
Planning And Assessment Funding 8,326.00
- . . B.0.b.1
Area Encompassed 136.0
- . . B.0.b.2
Stream Miles Affected .94
- . . B.1
Restoration Planning And CoordinationY (Y/N)
- . . . . B.1.a
Planning and Coordination funding 8,326.00
- . . . . B.1.b.11
Engineering/design work for restoration projectsY (Y/N)
- . . . . . . B.1.b.11.a
| Name of plan implemented | |
| WA Lower Columbia Salmon Recovery and Fish and Wildlife Subbasin Plan May 2010 Vol. II Ch. B. Estuary Tributaries Page 5 WA Lower Columbia Salmon Recovery and Fish and Wildlife Subbasin Plan May 2010 Vol. II Ch. B. Estuary Tributaries Page 5 |
- . . . . . . B.1.b.11.b
| Description and scope of the plan implemented | |
| Project will address a high priority fish passage barrier and allow access to upstream habitat for spawning, rearing, and refuge WA Lower Columbia Salmon Recovery and Fish and Wildlife Subbasin Plan May 2010 Vol. II Ch. B. Estuary Tributaries Page 5.
1. Restore Passage at Tide Gates, Culverts, and Other Artificial Barriers |
|
|