Deschutes Tributary Restoration Planning
Salmonid Restoration Planning and Assessments
|
20-1192 P | Puget Sound | 09/16/2020 | 06/06/2022 | 2020 | Completed | 05/01/2025 | |
| |
Description
This project was performed to identify, prioritize, and provide preliminary designs for actions that protect and restore a unique Deschutes River spring fed wetland and stream complex. This 22-acre tributary property belongs to the Meyer family, which worked with the project team to identify and implement protection and restoration actions that improve habitat quality while enabling them to continue farming their land (pasturing 8 cows, 2 horses). Restoration actions identified include removing three failing culverts, livestock exclusion fencing to protect streams and wetlands, instream LWD placement, and riparian restoration, along with a suite of farm management BMPs. We conducted a baseline fish use assessment and monitored water temperatures through summer 2021. The team began the permitting process, met on site with WDFW Habitat Bio, performed an assessment and wetland delineation.
Project Benefit
The project improves access to, and enhances the quality and quantity of, off-channel spawning and rearing habitat in the upper Deschutes watershed.
Funding Details |
PCSRF | $46,975 |
In-Kind Other | $1,500 |
Report Total: | $48,475 |
|
| |
Worksites
1-Meyer farm
- Worksite Identifier: 1-Meyer farm
- Start Date:
- End Date:
Area Description
No Area Description data was found for this worksite.
Location Information
- Basin: Puget Sound (171100)
- Subbasin:
- Watershed:
- Subwatershed:
- State: Washington
- Recovery Domain: Puget Sound
- Latitude: 46.79710228
- Longitude: -122.45798341
ESU
- Puget Sound/Strait of Georgia Coho Salmon ESU
- Puget Sound/Strait of Georgia Chum Salmon ESU
- Un-Named ESU Chinook
- Puget Sound Steelhead DPS
Map
Photos
Metrics
Metrics
- B.0
Salmonid Restoration Planning and AssessmentsY (Y/N)
- . . B.0.a
Planning And Assessment Funding 48,475.00
- . . B.0.b.1
Area Encompassed 22.0
- . . B.0.b.2
Stream Miles Affected .80
- . . B.1
Restoration Planning And CoordinationY (Y/N)
- . . . . B.1.a
Planning and Coordination funding 48,475.00
- . . . . B.1.b.11
Engineering/design work for restoration projectsY (Y/N)
- . . . . . . B.1.b.11.a
Name of plan implemented | |
1) Wild Fish Conservancy's WRIA 13 Phase IV Water Type Assessment final report (June 2019). It is also supported as a priority in: 2) the Deschutes R. Coho Salmon Biological Recovery Plan (Sept. 2015); and 3) the WRIA 13 2020 Recovery Strategy (2005). |
- . . . . . . B.1.b.11.b
Description and scope of the plan implemented | |
1) Specific project identified as a priority restoration action, Appendix A. 2) Project location, target species, and type identified as a priority throughout, esp. pp. 31-33. 3) Project location and type identified throughout, esp. p. 6. |
|
|