McDonald Creek Fish Passage Restoration
Salmonid Habitat Restoration and Acquisition
|
| 20-1142 R | | Puget Sound | | 09/23/2021 | | 12/31/2026 | | 2021 | | Ongoing | | 05/12/2026 | | |
| |
Description
The McDonald Creek Fish Passage project will rectify a long-known fish passage barrier and remove sources of fish mortality associated with operation of an irrigation diversion. The project will also improve habitat conditions, sediment, and wood transport in the creek. A small reinforced-concrete irrigation diversion dam with a Denil fishway is located at RM 3.2. Current site conditions are poor. A 2018 barrier assessment by WDFW documented that the dam is a complete barrier to fish and the Denil fishway was only deemed 33% passable for some adult fish. High velocity and turbulence likely make the existing fishway impassable to juveniles. All life stages of ESA-Listed Puget Sound Steelhead, as well as Coho, Cutthroat and Pacific Lamprey will benefit from this project. Improving fish passage will open up 4.5 and 6.1 miles of access to moderate to high quality habitat upstream of the dam for Coho and Steelhead, respectively, resulting in improved spawning and rearing habitat. The project will improve fish passage and enhance conditions for fish and wildlife while also improving Agnew Irrigation Districts ability to divert water according to their water right. This will be achieved by notching the dam, installing a new fish passage structure, and constructing rock weirs and pools below the dam. The existing open diversion canal will be replaced by a buried pipeline with a new head gate and debris rack; and the existing fish screen will be relocated to the new head gate area.
Project Benefit
The overall goal of the project is to improve fish passage and reduce fish mortality while maintaining and improving AID’s ability to divert water for irrigation according to their water right. This will be achieved by notching the dam, replacing the Denil fishway with a new fish passage structure for passage during irrigation operations, and constructing rock weirs and pools below the dam for passage outside of irrigation operations. The existing diversion canal will be replaced by a buried pipeline with a new head gate and debris rack; the existing fish screen will be relocated upstream to the new head gate area. ESA-Listed Puget Sound Steelhead, as well as Coho, Cutthroat and Pacific Lamprey will all benefit from this project. Coho and Steelhead spawn and rear both upstream and downstream of the diversion dam. All life stages of the four species will benefit from the project and the benefits will be realized year round. In addition, the project will improve sediment and wood transport through the dam to reduce degradation in downstream reaches and create better fish holding opportunities.
Accomplishments
| Instream Habitat |
| Stream Miles Treated |
|
.01 |
| Fish Passage |
| Barriers Removed |
|
1 |
| Miles Opened |
|
6.10 |
Funding Details |
| State | $406,415 |
| Other | $105,580 |
| Report Total: | $511,995 |
|
| |
Worksites
1-McDonald Creek
- Worksite Identifier: 1-McDonald Creek
- Start Date:
- End Date:
Area Description
No Area Description data was found for this worksite.
Location Information
- Basin: Puget Sound (171100)
- Subbasin:
- Watershed:
- Subwatershed:
- State:
- Recovery Domain: Puget Sound
- Latitude: 48.08902605
- Longitude: -123.23657307
ESU
- Puget Sound/Strait of Georgia Coho Salmon ESU
- Puget Sound/Strait of Georgia Chum Salmon ESU
- Puget Sound Steelhead DPS
Map
Photos
Metrics
Metrics
- C.0
Salmonid Habitat Restoration and AcquisitionY (Y/N)
- . . C.0.a
Habitat restoration and acquisition funding
- . . C.0.b
Length of stream treated/protected
- . . C.0.c
| Project identified in a Plan or Watershed Assessment | |
|
- . . C.0.d.1
Project Monitoring (LOV)
- . . C.0.d.2
Monitoring Location (LOV)
- . . C.2
Fish Passage ImprovementY (Y/N)
- . . . . C.2.a
Fish Passage Funding
- . . . . C.2.b.1
Length of stream made accessible
- . . . . C.2.b.3
Type of blockage/barrier (LOV)
- . . . . C.2.b.4
Number of blockages/impediments/barriers impeding passage
- . . . . C.2.c.1
Fish passage blockages removed or altered (other than road crossings reported in C.2.f to C.2.i)Y (Y/N)
- . . . . . . C.2.c.2
Number of blockages/impediments/barriers removed/altered
- . . . . C.2.e.1
Fish ladder installed/improvedY (Y/N)
- . . . . . . C.2.e.2
Number of fish ladders installed/improved
- . . C.3
Instream Flow ProjectY (Y/N)
- . . . . C.3.a
Instream Flow Funding
- . . . . C.3.b
Length of stream 'protected' for adequate flow
- . . . . C.3.c
Change in water flow (cfs)
- . . . . C.3.e.1
Irrigation practice improvementY (Y/N)
- . . . . . . C.3.e.2
Acre feet of water conserved per year (Acre feet)
- . . . . . . C.3.e.4
Initial start date of action or agreement (mm/dd/yyyy)
- . . . . . . C.3.e.5
Final end date of action or agreement (mm/dd/yyyy)
- . . C.4
Instream Habitat ProjectY (Y/N)
- . . . . C.4.a
Instream Habitat Funding
- . . . . C.4.b
Total length of instream habitat treated
- . . . . C.4.d.1
Channel structure placementY (Y/N)
- . . . . . . C.4.d.2
Material used for channel structure (LOV)
- . . . . . . C.4.d.3
Miles of stream treated through channel structure placement
- . . . . . . C.4.d.5
Pools expected to be created through channel structure placement
- . . . . . . C.4.d.7
Number of structures placed in channel
|
|