Alpowa PALS Phase III Restoration
Salmonid Habitat Restoration and Acquisition
|
20-1045 R | Snake River | 09/16/2020 | 12/31/2024 | 2018 | Completed | 05/01/2025 | |
| |
Description
This project resulted in 150 Post Assisted Log Structures being installed and then in the summer of 2024 we increased the number of logs in 10 structures by 3 or 4 pieces. The addition of wood on 10 structures resulted in more wood and larger structures. We estimate that at least 130 pools were formed and at least 450 pieces of wood were installed.
Project Benefit
Improve habitat diversity in Alpowa Creek. This will be achieved by installing PALS. PALS will increase instream complexity with additional woody debris and pool habitat for all live stages of steelhead.
Accomplishments
Instream Habitat |
Stream Miles Treated |
2.00 |
2.20 |
Funding Details |
PCSRF | $75,663 |
In-Kind Other | $14,753 |
Report Total: | $90,416 |
|
| |
Worksites
1-Alpowa Creek mainstem near
- Worksite Identifier: 1-Alpowa Creek mainstem near
- Start Date:
- End Date:
Area Description
No Area Description data was found for this worksite.
Location Information
- Basin: Lower Snake (170601)
- Subbasin:
- Watershed:
- Subwatershed:
- State: Washington
- Recovery Domain: Snake River
- Latitude: 46.42783683
- Longitude: -117.31714999
ESU
- Snake River Basin Steelhead DPS
Map
Photos
Metrics
Metrics
- C.0
Salmonid Habitat Restoration and AcquisitionY (Y/N)
- . . C.0.a
Habitat restoration and acquisition funding 90,416.34
- . . C.0.b
Length of stream treated/protected 2.00
- . . C.0.c
Project identified in a Plan or Watershed Assessment | |
|
- . . C.0.d.1
Project Monitoring (LOV)
- . . C.0.d.2
Monitoring Location (LOV)
- . . C.4
Instream Habitat ProjectY (Y/N)
- . . . . C.4.a
Instream Habitat Funding 90,416.34
- . . . . C.4.b
Total length of instream habitat treated 2.00
- . . . . C.4.d.1
Channel structure placementY (Y/N)
- . . . . . . C.4.d.2
Material used for channel structure (LOV)
- . . . . . . C.4.d.3
Miles of stream treated through channel structure placement 2.00
- . . . . . . C.4.d.4
Acres of streambed treated through channel structure placement 3.5
- . . . . . . C.4.d.5
Pools expected to be created through channel structure placement 130
- . . . . . . C.4.d.7
Number of structures placed in channel 150
|
|