Couse Cr Instream Habitat PA 79

Salmonid Habitat Restoration and Acquisition

Instream Habitat
Project ID20-1037 R
Recovery DomainsSnake River
Start Date09/16/2020
End Date12/31/2023
Year2020
StatusCompleted
Last Edited11/20/2024
 
1 - 1

Description    


The Couse Creek Project Area 79 (PA-79) Instream Habitat Project installed large woody debris structures including post assisted log structures (PALS), beaver dam analog structures (BDAs), and engineered wood structures. The project is located south of the City of Asotin, WA along Couse Creek Road. The project begins at river mile (RM) 1.4 and ends at RM 3.5. Couse Creek is listed as a minor spawning area (mSA) and priority protection reach that flows directly into the Snake River. LWD was added throughout the reach increasing geomorphic complexity, promote overbank flows, increase sediment, and increase water retention. Most of this reach of Couse Creek currently does not support perennial stream flows. The LWD structures were placed strategically to maximize the goals of the project, especially water retention.

Project Benefit    


This project improved stream function and increased habitat complexity for Snake River steelhead in Couse Creek. This project will help meet this goal by installing large wood structures and beaver dam analogues within the project area.

Accomplishments

Metric Completed Originally
Proposed
Instream Habitat
  Stream Miles Treated 2.10 2.10

Funding Details

SourceFunds
PCSRF$56,000
Other$42,970
In-Kind Volunteers$17,582
Report Total:$116,552


Project Map



Worksites

1-Couse Creek LWD Instream Ha    


  • Worksite Identifier: 1-Couse Creek LWD Instream Ha
  • Start Date:
  • End Date:
Area Description

No Area Description data was found for this worksite.

Location Information

  • Basin: Lower Snake (170601)
  • Subbasin: Lower Snake-Asotin (17060103)
  • Watershed: Captain John Creek-Snake River (1706010303)
  • Subwatershed: Couse Creek (170601030302)
  • State: Washington
  • Recovery Domain: Snake River
  • Latitude: 46.18752936
  • Longitude: -117.00113959

ESU

  • Snake River Basin Steelhead DPS

Map

Photos

Metrics

Metrics
  • C.0 Salmonid Habitat Restoration and AcquisitionY (Y/N)
    •      . . C.0.a Habitat restoration and acquisition funding 116,551.71
    •      . . C.0.b Length of stream treated/protected 2.10
    •      . . C.0.c
      Project identified in a Plan or Watershed Assessment
    •      . . C.0.d.1 Project Monitoring (LOV)
    •      . . C.0.d.2 Monitoring Location (LOV)
    •      . . C.4 Instream Habitat ProjectY (Y/N)
      •      . . . . C.4.a Instream Habitat Funding 116,551.71
      •      . . . . C.4.b Total length of instream habitat treated 2.10
      •      . . . . C.4.d.1 Channel structure placementY (Y/N)
        •      . . . . . . C.4.d.2 Material used for channel structure (LOV)
        •      . . . . . . C.4.d.3 Miles of stream treated through channel structure placement 2.10
        •      . . . . . . C.4.d.5 Pools expected to be created through channel structure placement 80
        •      . . . . . . C.4.d.7 Number of structures placed in channel 171