Santa Rosa Creek Restoration and Improved Land Management Design Project
Salmonid Restoration Planning and Assessments
|
| 1671664706984 | | S. California - S. Central CA Coast | | 06/01/2023 | | 02/10/2025 | | 2022 | | Terminated | | 10/14/2025 | | |
| |
Description
Grantee completed partial conceptual designs for two bridge alternatives. Conceptual in-channel restoration designs were not completed. The topographic basemap was delivered and one virtual Technical Advisory (TAC) meeting was held and two TAC site visits were conducted.
This agreement was terminated prior to completion due to capacity issues and a delayed timeline on agreement deliverables.
Project Benefit
The design process is stakeholder-inclusive in order to actualize multiple tangible and measurable project benefits that include addressing several known limiting factors to steelhead via riparian restoration and improvements to agriculture development. Steelhead will not be able to sustain for the long term without fast-tracking the identified habitat improvements. The TAC (Task 2) supports stakeholder/agency collaboration in order to progress toward recovery
Funding Details |
| PCSRF | $44,962 |
| In-Kind Donated Labor | $4,410 |
| Report Total: | $49,372 |
|
| |
Worksites
1671664707317
- Worksite Identifier: 1671664707317
- Start Date:
- End Date:
Area Description
Rhoades
Location Information
- Basin: Central California Coastal (180600)
- Subbasin:
- Watershed:
- Subwatershed:
- State: California
- Recovery Domain: S. California - S. Central CA Coast
- Latitude: 35.5747
- Longitude: -121.0299
ESU
- South-Central California Coast Steelhead DPS
Map
Photos
Metrics
Metrics
- B.0
Salmonid Restoration Planning and AssessmentsY (Y/N)
- . . B.0.a
Planning And Assessment Funding 49,372.00
- . . B.0.b.1
Area Encompassed .0
- . . B.0.b.2
Stream Miles Affected .00
- . . B.1
Restoration Planning And CoordinationY (Y/N)
- . . . . B.1.a
Planning and Coordination funding 49,372.00
- . . . . B.1.b.11
Engineering/design work for restoration projectsY (Y/N)
- . . . . . . B.1.b.11.a
| Name of plan implemented | |
| This grant was terminated early. Conceptual plans were submitted but infeasible to move forward with any of the alternatives. |
- . . . . . . B.1.b.11.b
| Description and scope of the plan implemented | |
| This grant was terminated early. Conceptual plans were submitted but infeasible to move forward with any of the alternatives. |
|
|