Lagunitas Creek Coho Habitat Enhancement Plan - 100% Designs for Phase 2 Sites (7, 8, 9, 10, 11)

Salmonid Restoration Planning and Assessments

Restoration Planning And Coordination
Project ID1702410918054
Recovery Domains -
Start Date05/23/2024
End Date06/30/2026
Year2023
StatusOngoing
Last Edited12/03/2025
 
1 - 1

Description    


Marin Water is seeking funding to complete final (100%) design plans, environmental compliance, and permitting of five habitat restoration sites in Lagunitas Creek. These sites have been identified as high priority through Marin Waters Lagunitas Creek Enhancement Plan (CDFW contract Q1996056) and have 30% design plans completed. All five sites are located in high-usage Coho Salmon spawning and rearing reaches of Lagunitas Creek within Samuel P. Taylor State Park downstream of Peters Dam.

Project Benefit    


Adding large wood and gravel to Lagunitas Creek will create complex self-maintaining riffle-pool habitat with cover and topographic complexity. Additionally, the structures are being designed to capture and sort spawning gravel. This project will create favorable spawning and rearing habitat in close proximity, thus improving early life stage survival for Coho Salmon and other salmonids.

Accomplishments

Metric Completed Originally
Proposed

Funding Details

SourceFunds
PCSRF$599,689
In-Kind Donated Labor$50,000
Report Total:$649,689


Project Map



Worksites

1702410918445    


  • Worksite Identifier: 1702410918445
  • Start Date:
  • End Date:
Area Description
Lagunitas Creek Habitat Enhancement Reach

Location Information

  • Basin:
  • Subbasin:
  • Watershed:
  • Subwatershed:
  • State:
  • Recovery Domain:
  • Latitude: 38.021728
  • Longitude: -122.73442

ESU

  • Central California Coast Coho Salmon ESU
  • Central California Coast Steelhead DPS

Map

Photos

Metrics

Metrics
  • B.0 Salmonid Restoration Planning and AssessmentsY (Y/N)
    •      . . B.0.a Planning And Assessment Funding .00
    •      . . B.0.b.1 Area Encompassed
    •      . . B.0.b.2 Stream Miles Affected
    •      . . B.1 Restoration Planning And CoordinationY (Y/N)
      •      . . . . B.1.a Planning and Coordination funding
      •      . . . . B.1.b.11 Engineering/design work for restoration projectsY (Y/N)
        •      . . . . . . B.1.b.11.a
          Name of plan implemented
        •      . . . . . . B.1.b.11.b
          Description and scope of the plan implemented